No Quick Solutions.....
February 25, 2008

Met with the prime engineering consultant for two days last week to discuss the yet to be awarded Phase II portion of the project. Re-examined changes requested and suggested, visited newly converted lift station as well as an un-converted site to provide a comparison. Prime consultant's SCADA specialist performed a site visit of the data center housing the central SCADA installation as well as our facilities.

The objective now is to get the original sub-consultant to modify and re-issue the plans and specifications for a rebid of this phase.

Received a call from the Phase II sub-consultant looking for a status report on all this; redirected to the prime consultant.

The wheels continue to turn slowly.....

Posted by Stan Prutz on February 25, 2008 | Comments (0)



POST A COMMENT
Display Name or Registered Users Login Here.

Before submitting this form, please type the characters displayed above:


Advertisement



Advertisements



About Us   |   Advertising Info   |   Site Map   |   Contact Us   |   Useful Sites   |   FREE Subscription   |   RSS
© 2008 Reed Business Information, a division of Reed Elsevier Inc. All rights reserved.
Use of this Web site is subject to its Terms of Use | Privacy Policy
Please visit these other Reed Business sites