Real Delays
October 23, 2007

October 23rd by Stan Prutz

Pardon my absence. My last entry talked about real progress. This has been followed with real delays!

The RTU manufacturer received an order for the Pump Station 3 RTU just after the last posting, but has yet to ship. They are thorough and are doing a good job with the details, but not moving very fast. City called today asking when we were going to get this all installed (we originally thought mid October with a 2 week shipment on the RTU) - that appears to have been wishful thinking. I'll guess mid-November now for the initial install.

Personally there have been delays as well. I thought I'd be walking 4 weeks ago - only got the OK yesterday. After you've gone 11-12 weeks without walking on a leg, it doesn't work quite the same. Muscles tighten up, range of motion diminishes - so, on to physical therapy....

The primary consultant continues to work on a control system master plan incorporating all pump stations and treatment plants. Pretty slow going there as well.

Posted by on October 23, 2007 | Comments (0)



POST A COMMENT
Display Name or Registered Users Login Here.

Before submitting this form, please type the characters displayed above:


Advertisement



Advertisements



About Us   |   Advertising Info   |   Site Map   |   Contact Us   |   Useful Sites   |   FREE Subscription   |   RSS
© 2008 Reed Business Information, a division of Reed Elsevier Inc. All rights reserved.
Use of this Web site is subject to its Terms of Use | Privacy Policy
Please visit these other Reed Business sites