Recent Posts
- Moving Forward
- How Best to Proceed?
- No Quick Solutions.....
- A Step Closer
- Back to Work 2008
- Spec Conflicts Solved With Creative Solutions
- 1st New RTU Commissioned
- A QDS Systems Quality Solution
- A Common Interest
- Real Delays
Archives
- April 2008
- March 2008
- February 2008
- January 2008
- December 2007
- November 2007
- October 2007
- September 2007
- August 2007
- July 2007
- June 2007
- May 2007
- April 2007
- March 2007
- February 2007
- January 2007
Blog
Moving Forward
April 30, 2008
April 30th by Stan Prutz
It appears we are moving toward some action regarding the hung Phase II portion of this project. The primary consultant is presenting a draft of an RFP this week for the City's review. The scope is expected to include modifying existing panels rather than replacing them, employing the City's preferred and widely installed special purpose RTUs. This is likely to be similar to the recently completed pump station completed on an emergency basis (see December entries) which served as the test case for modify rather than replace.
The timeline we have heard is to have proposals in within the next two months. Time will tell.
How does this affect other involved parties? We discussed last blog entry the Phase I successful RTU vendor paying a visit to top management within the wastewater department. Nothing substantial has resutled from that meeting. This vendor is now being told that although the City still wants their RTUs, their existing Phase I contract will be cancelled as part of the Phase II rebid. Seems it has been decided there are now too many contracts involved in this project (AMEN!).
Posted by Stan Prutz on April 30, 2008 | Comments (0)