Could PV installations really have reached 26 GW in 2011?

The simple answer is yes. Certainly enough modules and inverters were sold, and if installations really did hit 7.5 GW in Germany then this would undoubtedly mean that at least 26 GW was installed globally last year, with Germany retaining its position as the largest market, followed closely by Italy.

01/16/2012


We’re still finalizing our data for 2011, but we now estimate up to 26.5 GW could have been installed last year following the phenomenal year-end rally in Germany. This would have meant an incredible 10 GW was installed in the last quarter of the year – the first time this has ever happened and more than the whole amount installed in all of 2009!

As well as raising our estimates for 2011 global PV installations we’ve also increased our forecast to 26-28 GW for 2012, following the largely unexpected news of December installations hitting 3 GW in Germany, as well as better than expected performance in other key markets. Late last week, we released an extraordinary update to our clients providing updated installation data for 2011 and new projections for 2012 based on new information, which contained quite a few surprises.

Although we had been predicting 2011 installations of 6-8 GW for Germany throughout the year, the result of 7.5 GW was even higher than our most-likely scenario forecast, and much higher than every other analyst predicted. However it was also the slightly higher than expected installations in Italy, UK and China which proved important markets in determining the global outcome for 2011.

Most module and inverter suppliers will be extremely surprised at this huge market size for 2011, mainly because they didn’t see the year-end rally coming. As channel inventory was already extremely high going into Q4, there was already plenty of modules and inverters to serve the booming demand and most suppliers only saw a moderate increase (or even a decrease) in orders, as most of the action was happening further down the supply chain.

How big 2011 really was is going to remain a contentious issue. In fact, there’s not many industries that fail to agree on their market’s size by such a great margin, as there’s so many different methods of figuring out the size of true demand (installations, registrations, connections, shipments, etc…). This isn’t helped by some of the largest markets’ official statistics giving confusing and contradictory accounts of how much was actually installed in the prior quarter or year. Italy’s GSE for example still shows a 2010 market of both 2.3 GW and 5.8 GW for the same year in their reports! Based on our analysis of what could have really been physically installed in Italy in 2010, leads us to installations in the country of 4.4 GW in 2010 and a huge 7 GW in 2011.

The UK was another market to take many by surprise. We were considered bullish when we said back at the start of 2010 that at least 250 MW would be installed in 2011 due to the new tariff. Many were surprised by our prediction and disagreed the UK would grow this quickly. I even accepted a bet with the CEO of a major manufacturer who said this would never happen when he called me up on the prediction in late 2010 (you can’t not like a bet when involved in predicting the PV industry!). Now we’re finishing up our analysis of the UK market and we’re estimating around 800 MW was in fact installed here last year – quite an incredible feat!

Profile photo of Ash Sharma, senior research director for photovolatics at IMS Research. Courtesy: IMS ResearchSo what does 2012 hold for the PV industry? Well, we consider flat shipments of another 26 GW as being probable, but we also see upside potential of up to 29 GW of new installations this year. On the other hand, some downside potential also exists. How successful 2012 turns out largely depends on what the German and Italian governments do now – it is clear that way more PV capacity was added than they had budgeted for; and what the Chinese (both the suppliers and the Government) do in response.

It is also clear that 2011 was another record year for the industry with an almost unthinkable amount of new capacity added – it just shows what a big difference a mild winter in Europe makes to the PV industry –perhaps we will need to start forecasting the weather as well as the decision-making of politicians! 



No comments
The Engineers' Choice Awards highlight some of the best new control, instrumentation and automation products as chosen by...
Each year, a panel of Control Engineering editors and industry expert judges select the System Integrator of the Year Award winners.
Control Engineering Leaders Under 40 identifies and gives recognition to young engineers who...
Learn more about methods used to ensure that the integration between the safety system and the process control...
Adding industrial toughness and reliability to Ethernet eGuide
Technological advances like multiple-in-multiple-out (MIMO) transmitting and receiving
Virtualization advice: 4 ways splitting servers can help manufacturing; Efficient motion controls; Fill the brain drain; Learn from the HART Plant of the Year
Two sides to process safety: Combining human and technical factors in your program; Preparing HMI graphics for migrations; Mechatronics and safety; Engineers' Choice Awards
Detecting security breaches: Forensic invenstigations depend on knowing your networks inside and out; Wireless workers; Opening robotic control; Product exclusive: Robust encoders
The Ask Control Engineering blog covers all aspects of automation, including motors, drives, sensors, motion control, machine control, and embedded systems.
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
News and comments from Control Engineering process industries editor, Peter Welander.
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
This is a blog from the trenches – written by engineers who are implementing and upgrading control systems every day across every industry.
Anthony Baker is a fictitious aggregation of experts from Callisto Integration, providing manufacturing consulting and systems integration.
Integrator Guide

Integrator Guide

Search the online Automation Integrator Guide
 

Create New Listing

Visit the System Integrators page to view past winners of Control Engineering's System Integrator of the Year Award and learn how to enter the competition. You will also find more information on system integrators and Control System Integrators Association.

Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Control Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.