Direct current solution in Switzerland is said to provide maximum energy efficiency and minimum environmental impact for the green.ch data center facility. Validus DC Systems, an ABB company, will work on the project, saving up to 30%.
ABB will reportedly design and install an advanced, dc power distribution system for green.ch, an information and communications technology (ITC) service provider in Switzerland.
The dc technology is said to trim power conversion losses and is 10% to 20% more energy efficient than traditional ac technology for electrical distribution in data centers. The dc systems are also less complex and require less space, reducing equipment, installation, real estate and maintenance costs, resulting in a saving on total facility costs of up to 30%, according to ABB.
ABB will reportedly install a redundant 1 MW dc power distribution solution for the 1,500 m2 expansion of the existing 3,300 m2 data center. It will be designed and engineered to green.ch’s stringent ecological standards by Validus DC Systems, an ABB company. The order includes a service level agreement, and the expansion is scheduled to begin commercial operation in the first quarter of 2012.
Located in the municipality of Lupfig, in north-central Switzerland, the green.ch data center provides customers with secure storage and data management capabilities. The green.ch data center has been selected as ABB’s demonstration site for its new dc technology. It will be used as a showcase for international data center customers seeking to profit from this groundbreaking technology by reaching new benchmarks in energy efficiency for data center technologies, according to ABB.
The project underlines ABB’s goal to expand dc power applications. In May 2011, ABB gained a controlling interest in Validus DC Systems, a leading provider of dc power infrastructure equipment. In 2010, ABB invested in Power Assure, a developer of power management and optimization software for data centers.
ABB
- Edited by Amanda McLeman, Control Engineering, www.controleng.com
Integrator Guide
| Search the online Automation Integrator Guide |
|
|
|
|
Visit the System Integrators page to view past winners of Control Engineering's System Integrator of the Year Award and learn how to enter the competition. You will also find more information on system integrators and Control System Integrators Association.
Case Study Database
Get more exposure for your case study by uploading it to the Control Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.
These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.
Click here to visit the Case Study Database and upload your case study.