Scoping automation and control projects

A decision to leverage the relatively small cost of a quality scope and solid conceptual design can create significant long term savings and achieve an optimum solution.

10/22/2012


The approach taken during front-end engineering feasibility studies and scope development frequently determines whether an industrial control project will be successful. Unfortunately, budgetary and timing constraints normally limit the approach and resources used during these critical phases of project development, which ultimately result in unanticipated costs, technical complications, and schedule delays during subsequent project implementation. 

For example, plant operations or maintenance personnel are routinely tasked with developing project scopes and capital budget estimates in a short period of time while continuing to support on-going, day-to-day plant operations. 

In such situations, operations or maintenance personnel often have little choice but to build a total installed cost (TIC) estimate based primarily upon budgetary quotations for major equipment (based themselves upon minimal, if any, technical requirements specification) but with minimal time allocated to all other aspects of the project’s TIC.

Although this approach can be good for initial project evaluation and preliminary screenings, when capital budget allocations and schedules are based upon such estimates, the following types of challenges tend to develop during project implementation:

• Compliance with detailed codes and technical design standards introduce costs and/or delays.
•  Strategic alternatives for truly optimum solutions, such as different technologies, creative implementation tactics, or other vendors’ product offerings, are not discovered until too late in the project schedule, typically after long-lead equipment has already been ordered and detailed design has started.
• Subtle, often unknown, technical design assumptions implicit in the original plan are proven invalid and result in costly changes or delays during implementation.
• Constructability, operability, or maintenance concerns are expressed in late stages, frequently during well-intentioned project reviews after detailed design has progressed and budgets have been established.

On the other hand, if you want to maximize your project success, here are some useful techniques:

• Leverage the relatively small cost of a quality scope and solid conceptual design to realize significant long term savings and achieve an optimum solution.
• Be confident that that the conceptual design basis for the estimate is based upon a workable solution.
• Identify any implicit, hidden, or critical technical assumptions in the conceptual design worthy of confirmation.
• Manage (reduce) the project scoping cost by making realistic but conservative assumptions regarding generally known or established details that are not likely to introduce unexpected costs or delays.
• Consult external resources that can fully commit to scope development under the direction of plant personnel who can then better support on-going operations while offering key objectives and insight.
• Work closely and collaborate with such external resources on a time and material basis so the external resources will be encouraged to offer a variety of alternatives for consideration by plant personnel.
• Review the conceptual design with operations, maintenance, and construction personnel before finalizing the capital budget.
• Leverage prior experiences and lessons learned of all available resources.
• Anticipate the effort required to analyze and address the additional level of numerous details as required during the transition from an “80% design” to a “100% design.”

With few exceptions, the incremental cost for a solid project scope and estimate will (a) yield a positive net present value to the project’s overall TIC and (b) be recovered during a more efficient and effective detailed design and development process as a result.

This post was written by Shane Hudson. Shane is principal engineer at MAVERICK Technologies, a leading system integrator providing industrial automation, operational support and control systems engineering services in the manufacturing and process industries. MAVERICK delivers expertise and consulting in a wide variety of areas including industrial automation controls, distributed control systems, manufacturing execution systems, operational strategy, and business process optimization. The company provides a full range of automation and controls services – ranging from PID controller tuning and HMI programming to serving as a main automation contractor. Additionally MAVERICK offers industrial and technical staffing services, placing on-site automation, instrumentation and controls engineers.



No comments
The Engineers' Choice Awards highlight some of the best new control, instrumentation and automation products as chosen by...
Each year, a panel of Control Engineering editors and industry expert judges select the System Integrator of the Year Award winners.
Control Engineering Leaders Under 40 identifies and gives recognition to young engineers who...
Learn more about methods used to ensure that the integration between the safety system and the process control...
Adding industrial toughness and reliability to Ethernet eGuide
Technological advances like multiple-in-multiple-out (MIMO) transmitting and receiving
Virtualization advice: 4 ways splitting servers can help manufacturing; Efficient motion controls; Fill the brain drain; Learn from the HART Plant of the Year
Two sides to process safety: Combining human and technical factors in your program; Preparing HMI graphics for migrations; Mechatronics and safety; Engineers' Choice Awards
Detecting security breaches: Forensic invenstigations depend on knowing your networks inside and out; Wireless workers; Opening robotic control; Product exclusive: Robust encoders
The Ask Control Engineering blog covers all aspects of automation, including motors, drives, sensors, motion control, machine control, and embedded systems.
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
News and comments from Control Engineering process industries editor, Peter Welander.
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
This is a blog from the trenches – written by engineers who are implementing and upgrading control systems every day across every industry.
Anthony Baker is a fictitious aggregation of experts from Callisto Integration, providing manufacturing consulting and systems integration.
Integrator Guide

Integrator Guide

Search the online Automation Integrator Guide
 

Create New Listing

Visit the System Integrators page to view past winners of Control Engineering's System Integrator of the Year Award and learn how to enter the competition. You will also find more information on system integrators and Control System Integrators Association.

Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Control Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.