Baseline your system or else

In this Automation System Integration blog post, Anthony Baker learns that the lack of data about how a system has been operating can create a moving target after an upgrade.

06/03/2013


Anthony’s customer required an architectural change to a control system to support some new functions, a conversion from a two PLC (programmable logic controller) system to a three PLC system. All the old interlocks were mapped and moved, and new interlocks added between PLCs. All the DA (data administrator) servers, Invensys Wonderware ArchestrA objects and Wonderware InTouch HMI software tags were reconfigured for the new setup. In short, all items in the checklist were complete.

The new architecture was installed Saturday morning, and a whole bunch of test cases were run over a three-day weekend, to make sure everything was still working, and to tweak all of the control timing for the new response time. Everything looked good, so Monday night, it’s time start-up production again. And everything looked good in production too; just some minor tweaks here and there. Not everything can be caught in testing, so this was expected.

Non-specific trend

On Tuesday evening the client appears:

Client: “We’re getting more products not sent to the right location.”

Immediately questions start running through Anthony’s head:

  • What could be causing this?
  • Are there mechanical issues?
  • Is the system not setup correctly?
  • Is there a communication or network issue? I think that has that happened before.
  • Why hasn’t this been brought up earlier? It looks like everything is running just fine.

After looking around for some possible causes, Anthony can’t really identify anything that is causing this issue.

Client: “We are still seeing more products showing up in incorrect locations.”

Anthony: “I can’t really find any issues, how much more product?”

Client: “More than before. We usually get 120/160/180 per shift, and now we’re seeing 160/180, but last shift we got 300.”

Anthony: “Well 300 seems like a lot more than usual. Something else must have gone wrong.”

Client: “Maybe it did. I don’t know really. I just know we’re seeing more than before these changes were put in.”

Moving target

By this point Anthony is tearing his hair out trying to find the problem.

Anthony’s manager: “You’re spending a lot of time on this. How are we going to know when we’re done?”

Anthony: “I don’t know. I’ve fixed a bunch of things that would have existed before the change, but they keep telling me that it’s more than before, or it’s too much in general.”

Anthony’s manager: “If now it’s too much, how much is right? 100? 50? 0? What’s the target here? Do we know for sure what they had before?”

Anthony: “I don’t know. They don’t have historical data. I heard one guy say six per shift was expected...”

This continued until all ideas were exhausted, along with Anthony. In the end, it got down to a count under 30 per shift, much lower than it was before, and the client was happy. Anthony fixed some things that had been in the code since nearly the beginning of the project, but hadn’t come up before.

Lessons learned

If you’re going to be making a change or improvement to a system make sure you have the baseline data on how it operated before, in production. Your test cases won’t always show all the problems on a complex system.

- Anthony Baker strikes again: Anthony Baker is a fictitious aggregation of experts from Callisto Integration, providing manufacturing consulting and systems integration. This blog provides integration advice in plant-floor controls, manufacturing execution systems (MES), and manufacturing consulting, from the factory floor through to the enterprise. Andrew Barker, P.Eng., Callisto Integration, compiled the advice. www.callistointegration.com

Callisto Integration is a CSIA member as of 3/1/2015



No comments
The Engineers' Choice Awards highlight some of the best new control, instrumentation and automation products as chosen by...
The System Integrator Giants program lists the top 100 system integrators among companies listed in CFE Media's Global System Integrator Database.
Each year, a panel of Control Engineering and Plant Engineering editors and industry expert judges select the System Integrator of the Year Award winners in three categories.
This eGuide illustrates solutions, applications and benefits of machine vision systems.
Learn how to increase device reliability in harsh environments and decrease unplanned system downtime.
This eGuide contains a series of articles and videos that considers theoretical and practical; immediate needs and a look into the future.
Controller programming; Safety networks; Enclosure design; Power quality; Safety integrity levels; Increasing process efficiency
Additive manufacturing benefits; HMI and sensor tips; System integrator advice; Innovations from the industry
Robotic safety, collaboration, standards; DCS migration tips; IT/OT convergence; 2017 Control Engineering Salary and Career Survey
Featured articles highlight technologies that enable the Industrial Internet of Things, IIoT-related products and strategies to get data more easily to the user.
This article collection contains several articles on how automation and controls are helping human-machine interface (HMI) hardware and software advance.
This digital report will explore several aspects of how IIoT will transform manufacturing in the coming years.

Find and connect with the most suitable service provider for your unique application. Start searching the Global System Integrator Database Now!

Infrastructure for natural gas expansion; Artificial lift methods; Disruptive technology and fugitive gas emissions
Mobility as the means to offshore innovation; Preventing another Deepwater Horizon; ROVs as subsea robots; SCADA and the radio spectrum
Future of oil and gas projects; Reservoir models; The importance of SCADA to oil and gas
Automation Engineer; Wood Group
System Integrator; Cross Integrated Systems Group
Jose S. Vasquez, Jr.
Fire & Life Safety Engineer; Technip USA Inc.
This course focuses on climate analysis, appropriateness of cooling system selection, and combining cooling systems.
This course will help identify and reveal electrical hazards and identify the solutions to implementing and maintaining a safe work environment.
This course explains how maintaining power and communication systems through emergency power-generation systems is critical.
click me