Blowout preventer overhaul way off

The blowout preventer that failed on a BP well last year was four years overdue for maintenance under driller Transocean Ltd.’s internal guidelines, a U.S. regulator said.

04/26/2011


The blowout preventer that failed on a BP well last year was four years overdue for maintenance under driller Transocean Ltd.’s internal guidelines, a U.S. regulator said.

The Deepwater Horizon’s blowout preventer had not been disassembled and refurbished since the rig was commissioned in 2001, said Jason Mathews of the U.S. Bureau of Ocean Energy Management, Regulation and Enforcement during an investigative hearing in Metairie, La.

Under Transocean’s own rules, there should have been an overhaul of the blowout preventer no later than the summer of 2006, Mathews said.

The preventer is a 300-ton stack of valves and pipes designed to stop an oil well from surging out of control.

In the Deepwater Horizon incident, the blowout preventer’s blades failed to sever and seal the pipe from BP’s Macondo well during the April 2010 disaster that killed 11 rig workers, sank the vessel, and spewed enough crude into the sea to fill two supertankers, according to a study commissioned by a joint US Coast Guard-Interior Department panel. Mathews is one of eight members of the panel.

The blowout preventer wasn’t in need of an overhaul, Michael Fry, a Transocean manager who oversees subsea equipment used on all of the company’s Gulf of Mexico rigs, told the panel.

“If it’s not found to be outside its operating tolerances, that piece of equipment stays in service,’’ Fry said.

A study of the blowout preventer, carried out by Det Norske Veritas, concluded a lack of maintenance work was not a factor in the failure of the blades to crimp the pipe. Cameron International Corp., based in Houston, made the blowout preventer used by the Deepwater Horizon.



No comments
The Engineers' Choice Awards highlight some of the best new control, instrumentation and automation products as chosen by...
Each year, a panel of Control Engineering editors and industry expert judges select the System Integrator of the Year Award winners.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
Learn how to increase device reliability in harsh environments and decrease unplanned system downtime.
This eGuide contains a series of articles and videos that considers theoretical and practical; immediate needs and a look into the future.
Learn how to create value with re-use; gain productivity with lean automation and connectivity, and optimize panel design and construction.
Go deep: Automation tackles offshore oil challenges; Ethernet advice; Wireless robotics; Product exclusives; Digital edition exclusives
Lost in the gray scale? How to get effective HMIs; Best practices: Integrate old and new wireless systems; Smart software, networks; Service provider certifications
Fixing PID: Part 2: Tweaking controller strategy; Machine safety networks; Salary survey and career advice; Smart I/O architecture; Product exclusives
The Ask Control Engineering blog covers all aspects of automation, including motors, drives, sensors, motion control, machine control, and embedded systems.
Look at the basics of industrial wireless technologies, wireless concepts, wireless standards, and wireless best practices with Daniel E. Capano of Diversified Technical Services Inc.
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
This is a blog from the trenches – written by engineers who are implementing and upgrading control systems every day across every industry.
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.

Find and connect with the most suitable service provider for your unique application. Start searching the Global System Integrator Database Now!

Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Control Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.