Carl R. Darnall Army Medical Center December update

Functional performance testing is being performed on the chilled water pumps, heating hot water pumps, heat recovery pumps, unit heaters, and domestic water booster pump skin in the central utility plant.

By Southland Industries December 3, 2014

December 2014 update:

  • North Clinic test and balance (TAB) is nearing completion.
  • South Clinic punchlist activities started on level 1 two weeks ago.
  • South Clinic TAB is underway.
  • Hospital basement and level 1 finish is nearing completion.
  • TAB on equipment being performed in the hospital basement and on level 1.
  • Kitchen equipment installation is continuing.
  • Functional performance testing is being performed on the chilled water pumps, heating hot water pumps, heat recovery pumps, unit heaters, and domestic water booster pump skin in the central utility plant.
  • Preparing to send steam throughout the hospital and clinics in order to start functional performance testing on the boiler system.