Dry-type transformer failures versus liquid transformer failures

In this "Cut the Copper" installment, Guentert explains how, when properly installed, liquid-filled transformers in data center power systems are more reliable than air-cooled dry-type transformers.

05/09/2012


I stated at the outset of this series that it would be controversial, and might receive a backlash of unfavorable response. Here is my most controversial statement, as clearly as I can state it:

In my opinion, after having carefully watched this situation develop over 35 years of my professional life, I’ve concluded that properly designed liquid-filled transformers, when installed in properly designed data center power systems, are more reliable than air-cooled dry-type transformers, when switched fairly frequently by upstream vacuum breakers, at voltages of 10 kV and above, by a factor of at least 50.

How’s THAT for being politically incorrect? Whenever I make this statement to a new client or to a group I’m presenting to, the immediate response is usually, “Show us some hard data to back up that terribly assertive claim you just made.”

The hard data don’t exist, I admit. I think that this is mostly because no data center owner ever reports its failures to any sort of a registry or information clearing-house, nor do transformer manufacturers want to report their failures, either. All I can do here is report my own personal experiences:

--I have personal knowledge of more than 75 failures of dry type transformers installed in data centers (95% of them VPI’s) under the switching circumstances described previously, over 35 years of experience. I’d have to believe that there are many, many more I haven’t heard about.

--I’ve personally investigated more than 30 failures of dry-type transformers under these conditions, at various sites—some at the request of my clients and employers, and some just out of my own curiosity.

--I have personally witnessed the failures of 5 indoor dry-type substation transformers at the instant of occurrence, while standing with 30 ft of each of them at the time, inside electrical rooms of active data centers. (Blinding flash, loud “BLAM!!!,” small flames, heavy black smoke, fire alarm callouts, fire companies running into electrical rooms with water hoses. Two of these failures occurred simultaneously, with a single breaker closure, in one data center.)

--I work closely with a select group of large general contractors, who specialize in construction of large data centers, and who have probably collectively built at least $8 billion of large new data centers in the past 5 years. Their guys know of my passion for this topic, and I generally receive about 5 or 6 phone calls or e-mails per year from them. E-mails like, “Hey, Joe. Two more today, at a data center in Virginia, about 1:30 p.m. Simultaneous loud flashover of two 2.5 mVA 12.47  kV VPI units, with a single breaker closure, during final Integrated Systems Testing. No snubbers were installed.”

--I’m aware of at least two manufacturers of dry-type and cast coil transformers who declared bankruptcy and closed up shop, under the weight of warranty claims and litigation from similar failures.

I’ve observed a fairly recent shift in attitude of the remaining major dry-type transformer manufacturers. On a failure of a 2.5 MVA VPI unit in a data center just two months ago, I heard the manufacturer’s response to a request to IMMEDIATELY provide a replacement transformer at no charge under warranty terms. Paraphrasing slightly:

“Warranty claim replacement is denied. This is not a manufacturing defect in our transformer covered by warranty…it’s a widely known systems problem with dry-type transformers switched by upstream vacuum breakers. There was no snubber installed on this transformer. Go speak with your consulting engineer about his system design problem.”



No comments
The Engineers' Choice Awards highlight some of the best new control, instrumentation and automation products as chosen by...
The System Integrator Giants program lists the top 100 system integrators among companies listed in CFE Media's Global System Integrator Database.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
This eGuide illustrates solutions, applications and benefits of machine vision systems.
Learn how to increase device reliability in harsh environments and decrease unplanned system downtime.
This eGuide contains a series of articles and videos that considers theoretical and practical; immediate needs and a look into the future.
Motor specification guidelines; Understanding multivariable control; Improving a safety instrumented system; 2017 Engineers' Choice Award Winners
Selecting the best controller from several viewpoints; System integrator advice for the IIoT; TSN and real-time Ethernet; Questions to ask when selecting a VFD; Action items for an aging PLC/DCS
Robot advances in connectivity, collaboration, and programming; Advanced process control; Industrial wireless developments; Multiplatform system integration
Motion control advances and solutions can help with machine control, automated control on assembly lines, integration of robotics and automation, and machine safety.
This article collection contains several articles on the Industrial Internet of Things (IIoT) and how it is transforming manufacturing.

Find and connect with the most suitable service provider for your unique application. Start searching the Global System Integrator Database Now!

Future of oil and gas projects; Reservoir models; The importance of SCADA to oil and gas
Big Data and bigger solutions; Tablet technologies; SCADA developments
SCADA at the junction, Managing risk through maintenance, Moving at the speed of data
Automation Engineer; Wood Group
System Integrator; Cross Integrated Systems Group
Jose S. Vasquez, Jr.
Fire & Life Safety Engineer; Technip USA Inc.
click me