Engineers put control valve to the test: Web exclusive

Pressure independent control valve solves instability problems, saves energy, and reduces equipment maintenance.

10/15/2012


Figure 1: For this test, the team replaced both the ball and manual balancing valve on a hot water supply line on the primary side of two plate and frame heat exchangers with a single Danfoss PICV and actuator. The system is responsible for producing hotIn hydronic HVAC systems made up of traditional balancing and control valves, system pressure is affected every time a valve changes its position. When the system pressure changes, the flow through all of the valves reacts and causes the amount of heat transfer through each device to also change. Assuming that each device was at equilibrium to start, we can deduce that each device is now getting either too much or too little heat transfer. As a result, each device requests that its valve open or close to compensate for the change in flow induced by the change in system pressure. 

Due to this chain reaction, HVAC systems with traditional valves can be inherently unstable, resulting in overflows and underflows at the terminal coils. In turn, this leads to wasted energy, suboptimal heat transfer, premature failure of equipment, and a less comfortable space for the building occupants. 

Figure 2: Starting with the valve completely closed (0%), the team began opening the valve in 5% increments until completely open (100%); the team then reversed the procedure, incrementally closing the valve from 100% open to completely closed. The resultThe engineering team at Rochester Institute of Technology (RIT) wanted to investigate an alternate HVAC design that could improve the stability of its system. Its research suggested a relatively new technology called a pressure independent control valve (PICV), which is able to absorb system pressures to maintain a constant desired flow rate at all times. In theory, if a PICV functions properly, then changes in system pressure will not cause flow changes through the valves—thus solving the instability issues. 

PICV testing setup

The RIT team set out to test this theory in October 2011 by installing one PICV in its facility and carefully monitoring the results.

It selected a hot water supply line supplying 240 F to two plate and frame heat exchangers that make hot water for a 160,000-sq-ft academic building. This line has an existing two-way full port ball valve and a manual balancing valve on the primary side of the heat exchangers (see Figure 1). In the past, this line exhibited the classic characteristics of typical HVAC systems: instability issues, large swings in temperatures, and valve “hunting.”

Figure 3: The team repeated the test opening and closing the valve incrementally, but this time varied the pressure at the supply plant, resulting in excellent linear response from the valve at almost all test points. Courtesy: Rochester Institute of TechFor the purposes of the test, the engineering team replaced both the ball valve and the manual balancing valve with a single Danfoss PICV and actuator. The setup comprised the following items:

  • One 4-in. Danfoss AB-QM PICV (167 gpm) with a matching Danfoss modulating actuator (2 to 10 V)
  • The PICV installed on the primary side of a plate and frame heat exchanger using medium-temperature hot water (MTHW) at 240 F delivering hot water to the building
  • A GE AT868 ultrasonic meter (with a rated accuracy of +/-2%) installed on the pipe to measure flow rates
  • Automated Logic Controls WebCTRL System used to control the valve and record the flow meter measurements  

It is important to note that the tests were conducted on a live system, not in a laboratory setting. The test PICV was used to control the temperature of the water to an occupied building under normal operating conditions. 

Figure 4: When the team kept the valve position constant (40% open) while varying the plant pressure, the PICV held the desired flow despite the significant changes in system pressure. The red line indicates the flow as the pressure was increased from 6 pFlow stability at standard system pressure 

The first series of tests was conducted by sending the valve actuator different control signals and measuring the resulting flow on the GE ultrasonic meter using the normal operating system pressure.

Testing started with the valve completely closed (0%), and then the team began opening the valve in 5% increments until completely open (100%). Next, it reversed the procedure, starting with the valve completely open (100%) and closing in 5% decrements until completely closed (0%). As shown in Figure 2, at standard system pressure the flow had the desired linear response as the valve was opening or closing. However, since the team did not change the system pressure, it had not yet tested the pressure independence feature. 

Figure 5: The PICV held setpoint temperature with very little valve movement. This can be compared to the old ball valve which fluctuated wildly in response to system pressure changes. Courtesy: Rochester Institute of TechnologyFlow stability at varied system pressures 

In this test, the team again opened and closed the valve incrementally but this time varied the system pressure at the supply plant. Figure 3 shows the excellent linear response from the valve at almost all the test points. 

The valve did not always deliver the expected flow when the differential pressure at the valve did not meet the manufacturer’s stated minimum pressure rating of 4 psi. For example, when the system pressure was 10 psi and the valve was 85% open, the differential pressure at the valve would fall to between 3.1 and 3.6 psi. This is below the minimum requirement for full linear control and caused some loss of valve authority. It is worth noting that this situation of high flow and low system pressure would be unlikely to occur in actual operation. During high demand periods, the plant pressure would be at least 15 psi or more. In all test points that reflected actual plant operation, the linearity and control authority were well maintained. 

Figure 6: The PICV held the actual water temperature very close to setpoint temperature with very small flows compared to the old ball valve. This leads to more stable water temperatures and lower energy costs. It can be seen here that the water temperatuConstant flow maintained

In the final test, the engineering team kept the valve position constant while varying the plant pressure to see if the valve would compensate for the pressure changes and keep the flow constant. The valve was held at 40% open and the plant system pressure was varied up and then down (see Figure 4). 

The PICV held the desired flow despite significant changes in system pressure. Only at the very low end of the system pressure range did the flow start to slightly drop due to the fact that the pressure at the valve was starting to approach the manufacturer’s minimum pressure rating. 

The results of the team’s analysis showed that as long as the pressure across the valve body is within the stated pressure range and the valve position is more than 10% open, the flow through the valve is almost perfectly linear regardless of system pressure. 

Several months after the valve had been installed in RIT’s academic building, the team reports that the performance has been excellent. The control stability has been outstanding as the valve maintains temperature very well with very little valve movement. Normal changes in the plant system pressure do not affect the valve operation; this is especially evident at minimal positions where traditional valves had been particularly unstable. Figure 5 clearly illustrates the difference in performance between the old ball valve and the new PICV. Furthermore, Figure 6 shows the actual performance of the PICV in terms of holding set temperature with very little movement of the valve, demonstrating the power of a pressure independent valve. 

Ultimately, the result of improving the stability of the building’s hydronic system will be energy savings, better temperature stability for building occupants, and less valve and actuator maintenance as a result of less movement in these components. RIT is planning to make PICVs a standard in its future new builds and renovations. 

 


Timothy Vann is a member of the Rochester Institute of Technology Facilities Management Services engineering team. He has a bachelor’s in mechanical engineering and is an experienced computer programmer, HVAC design engineer, and control system engineer. RIT student Taylor Osmonson assisted in gathering information for this project.



No comments
The Engineers' Choice Awards highlight some of the best new control, instrumentation and automation products as chosen by...
Each year, a panel of Control Engineering editors and industry expert judges select the System Integrator of the Year Award winners.
Control Engineering Leaders Under 40 identifies and gives recognition to young engineers who...
Learn more about methods used to ensure that the integration between the safety system and the process control...
Adding industrial toughness and reliability to Ethernet eGuide
Technological advances like multiple-in-multiple-out (MIMO) transmitting and receiving
Virtualization advice: 4 ways splitting servers can help manufacturing; Efficient motion controls; Fill the brain drain; Learn from the HART Plant of the Year
Two sides to process safety: Combining human and technical factors in your program; Preparing HMI graphics for migrations; Mechatronics and safety; Engineers' Choice Awards
Detecting security breaches: Forensic invenstigations depend on knowing your networks inside and out; Wireless workers; Opening robotic control; Product exclusive: Robust encoders
The Ask Control Engineering blog covers all aspects of automation, including motors, drives, sensors, motion control, machine control, and embedded systems.
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
News and comments from Control Engineering process industries editor, Peter Welander.
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
This is a blog from the trenches – written by engineers who are implementing and upgrading control systems every day across every industry.
Anthony Baker is a fictitious aggregation of experts from Callisto Integration, providing manufacturing consulting and systems integration.
Integrator Guide

Integrator Guide

Search the online Automation Integrator Guide
 

Create New Listing

Visit the System Integrators page to view past winners of Control Engineering's System Integrator of the Year Award and learn how to enter the competition. You will also find more information on system integrators and Control System Integrators Association.

Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Control Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.