If you’ve been in controls long enough, it’s happened to you: a project that seemed to be going well suddenly hits a wall that was unforeseen and whose effects threaten to derail it irreversibly. My Waterloo came with a project to automate a press that made abrasive bars for honing pipe welds, compressing sand-like material into rectangular “sticks” that were then baked to produce the final product.

 

System IntegrationThe automation portion was reasonably straightforward, applying mechanical and controls equipment that would feed the raw material into the die cavities, compress it and automatically offload the pressed sticks to small pallets. The usual risks were identified and hedged: subcontractor performance issues, equipment delays, personnel scheduling, etc. What doomed the project was my failure to heed a small, offhand comment made by the client even before the project began about how difficult the raw material was to work with, and how its properties changed from day-to-day and even hour-by-hour. 

 

Previously, operators ran the press manually feeding the die cavities by hand using a small shoe holding the raw material. If the raw material was wet or fed poorly into the dies, the operator could agitate the shoe more vigorously. If it fed smoothly, a quicker motion was used. 

 

Our machine functioned flawlessly in dry trials. Hopper feeders fed. Feed shoes indexed. Presses pressed. Manipulators picked and placed the “ghost” sticks perfectly. Conveyors conveyed. We were ready for our dress rehearsal.

 

At least we thought we were ready. The raw material ignored the law of gravity. It obstinately refused to fall into our die cavities as commanded. Voids were the rule, not the exception, and irregular sticks crumbled when picked up. We made adjustments and, just as we managed to get things working, the properties of the raw material changed as it dried and we were thrown back to square one. All the while the client’s remark about how stubborn the material could be haunted us. In retrospect, it was clear we should have run offline trials with the range of materials we would encounter in actual operation. We were too trusting in gravity. 

 

Things eventually turned around and we ended the project on a high note. We managed to make the system work throughout the range of materials and properties presented to us, albeit after several redesigns of the feed system, multiple delays, and a tired project team. It was a hard lesson, but one from which we all learned and have used since to prevent a replay.

 

The moral of the story: Listen carefully to the process owners in the early stages of a project. They know their processes and have seen the full gamut of problems with equipment, materials, and processes. Problems can be overcome through the intelligent application of engineering, but only if one fully comprehends them, plans for them, and avoids going too far down the wrong path.

 

This post was originally written by Brad Ems. Brad is a project manager at MAVERICK Technologies, a leading system integrator providing industrial automation, operational support and control systems engineering services in the manufacturing and process industries. MAVERICK delivers expertise and consulting in a wide variety of areas including industrial automation controls, distributed control systems, manufacturing execution systems, operational strategy, and business process optimization. The company provides a full range of automation and controls services – ranging from PID controller tuning and HMI programming to serving as a main automation contractor. Additionally MAVERICK offers industrial and technical staffing services, placing on-site automation, instrumentation and controls engineers.



No comments
The Engineers' Choice Awards highlight some of the best new control, instrumentation and automation products as chosen by...
Each year, a panel of Control Engineering editors and industry expert judges select the System Integrator of the Year Award winners.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
Learn how to increase device reliability in harsh environments and decrease unplanned system downtime.
This eGuide contains a series of articles and videos that considers theoretical and practical; immediate needs and a look into the future.
Learn how to create value with re-use; gain productivity with lean automation and connectivity, and optimize panel design and construction.
Go deep: Automation tackles offshore oil challenges; Ethernet advice; Wireless robotics; Product exclusives; Digital edition exclusives
Lost in the gray scale? How to get effective HMIs; Best practices: Integrate old and new wireless systems; Smart software, networks; Service provider certifications
Fixing PID: Part 2: Tweaking controller strategy; Machine safety networks; Salary survey and career advice; Smart I/O architecture; Product exclusives
The Ask Control Engineering blog covers all aspects of automation, including motors, drives, sensors, motion control, machine control, and embedded systems.
Look at the basics of industrial wireless technologies, wireless concepts, wireless standards, and wireless best practices with Daniel E. Capano of Diversified Technical Services Inc.
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
This is a blog from the trenches – written by engineers who are implementing and upgrading control systems every day across every industry.
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.

Find and connect with the most suitable service provider for your unique application. Start searching the Global System Integrator Database Now!

Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Control Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.