Hospital meets critical power needs

Phoenix Children's Hospital's emergency power supply system must meet emergency standby requirements for both a healthcare facility and a high-rise building.

Shawn Grimm, PE, ccrd partners

09/15/2011


Phoenix Children’s Hospital in Phoenix is both a healthcare facility and a high-rise building. As such, the facility’s emergency power supply system (EPSS) must meet emergency standby requirements for both types of facilities. To meet these requirements the facility has a remote central energy plant housing most of its EPSS. The emergency power supply (EPS) consists of three 2 MW generators and medium-voltage paralleling gear and distribution. Unit substations are located throughout the facility with automatic transfer switches (ATS) located downstream of unit substation. Any of the three 2 MW generators can accommodate the requirements of NFPA 70 and NFPA 99 for the life safety branch and critical branch for the entire facility. There are also a variety of stored emergency power supply systems (SEPPSS).

With more than 1 million sq ft of space, the campus expansion will make Phoenix Children’s Hospital one of the largest freestanding children’s hospitals in the country. Courtesy: ccrd partners

The EPSS serves all of the required fire protection and life safety systems including voice communications, fire detection and alarm system, electric fire pump, emergency fire command center, exit signs, means of egress illumination, power operated doors, and mechanical stair shaft ventilation systems for smoke-proof enclosures. The EPSS also serves all other functions required under NFPA 70 Article 517.

There are a variety of SEPSS battery systems used throughout the facility. There is a central inverter to provided egress lighting in the main lobby, emergency battery ballast used in rooms where patients are anesthetized, and a centralized UPS for the data center.

This shows the paralleling gear in Phoenix Children’s Hospital emergency switchgear room. Courtesy: ccrd partners

Multiple system tests were performed to ensure that each of the required systems would operate correctly when different events occurred. A variety of different test were conducted including power outages, remote power transfer on ATS from the command center, smoke detector activation, pull station activation, duct detectors activation, and fire pump test to ensure the proper system function.

Grimm is associate principal and project manager with ccrd partners in the Phoenix office. He is the lead electrical engineer, and leads the electrical design of different projects including hospitals, institutional facilities, and office buildings.



No comments
The Engineers' Choice Awards highlight some of the best new control, instrumentation and automation products as chosen by...
Each year, a panel of Control Engineering editors and industry expert judges select the System Integrator of the Year Award winners.
Nominate today - Control Engineering Leaders Under 40 identifies and gives recognition to young engineers who...
Learn more about methods used to ensure that the integration between the safety system and the process control...
Adding industrial toughness and reliability to Ethernet eGuide
Technological advances like multiple-in-multiple-out (MIMO) transmitting and receiving
Robotic innovations, safety, Industrial energy management, Lambda tuning for PID, HMIs: All about software
CNC Way beyond traditional; Remote I/O, new approaches; Inside Process: APC, PID, cyber-security
Servodrive Control: Precise Power, PLCs vs. PACs, Virtualization, Best Products: Engineers' Choice Awards
The Ask Control Engineering blog covers all aspects of automation, including motors, drives, sensors, motion control, machine control...
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
News and comments from Control Engineering process industries editor, Peter Welander.
Integrator Guide

Integrator Guide

Search the online Automation Integrator Guide
 

Create New Listing

Visit the System Integrators page to view past winners of Control Engineering's System Integrator of the Year Award and learn how to enter the competition. You will also find more information on system integrators and Control System Integrators Association.

Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Control Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.


Poll of the Week

How integrated are your maintenance, controls, and instrumentation systems?
Fully integrated
Somewhat integrated
Loosely integrated
They're not


Click Here for Poll Archives
Sponsored by:

CFEMedia.com | Subscribe to Magazine | Advertise | Contact Us | About Us | Site Map | Privacy Policy
Channels | New Products | Media Library | Connect | Industry News | Events and Awards | Newsletters | Blogs | Magazine
Control Engineering | Plant Engineering | Consulting-Specifying Engineer
All content copyright © 2010-2013 CFE Media. All rights reserved.