LEED 2012 for data centers and healthcare

In an effort to be more market-focused, LEED 2012 tackles data centers and hospitals, buildings that often have a more difficult time achieving LEED certification because of their significant energy and uptime demands.

03/13/2012


In an effort to be more market-focused, LEED 2012 tackles data centers and hospitals, buildings that often have a more difficult time achieving LEED certification because of their significant energy and uptime demands. LEED 2012 gives these buildings a different benchmark by which to measure their energy savings, recognizing that reduction is difficult and therefore providing them more of an opportunity to achieve it.

Data centers

EA Prerequisite 1: Combined building and IT energy use must be 10% less than the ASHRAE 90.1-2010 baseline. Power utilization effectiveness (PUE) must be reported and two systems must be modeled: one for the building’s energy costs and another for IT energy costs. PUE is the ratio of total data center energy use including process loads to regulated energy use (HVAC and lighting). Finally, a 30% energy savings from the data center’s nonprocess load, i.e., building power and cooling infrastructure, must be documented.

EA Credit – Enhanced Commissioning: Depending on the size of the peak cooling load, additional design and submittal reviews are required. For projects with peak cooling loads of <2 million Btuh or a total computer room peak cooling load of < 600,000 Btuh, the commissioning agent must conduct design reviews, including reviews of the OPR and BOD, at 95% design development and at 50% construction design. For projects with peak cooling loads of >2 million Btuh or total computer room peak cooling loads of >600,000 Btuh, the commissioning agent will conduct design reviews, including reviews of the OPR and BOD, prior to the start of the design, at 100% design development, and at 50% construction design.

Healthcare

EA Credit – Optimized Energy Performance: Typical buildings can be awarded up to 18 LEED points, but with LEED 2012, hospitals can now earn up to 20 points. Because hospitals have such large process loads and larger outside air requirements than typical commercial buildings, LEED 2012 will reward a hospital with more points for energy reductions similar to other building types. For example, a 12% reduction in energy expenditure will earn a hospital an extra point over a 12% reduction for another building type.

Vallort leads the Energy + Eco Services group at ESD. Vallort has served as project manager, commissioning agent, design engineer, and LEED consultant on various projects ranging from multimillion-dollar campus-wide projects to individual site commissioning services. Lorenz serves as a project manager and sustainability specialist for ESD. As the LEED consultant on many projects, Lorenz helps buildings optimize building energy performance as well as meet LEED documentation and certification requirements.



No comments
The Engineers' Choice Awards highlight some of the best new control, instrumentation and automation products as chosen by...
The System Integrator Giants program lists the top 100 system integrators among companies listed in CFE Media's Global System Integrator Database.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
This eGuide illustrates solutions, applications and benefits of machine vision systems.
Learn how to increase device reliability in harsh environments and decrease unplanned system downtime.
This eGuide contains a series of articles and videos that considers theoretical and practical; immediate needs and a look into the future.
Additive manufacturing advancements; Machine vision enhances robotics; Fieldbus evolution; Process safety; Advice from System Integrators of the Year; Road to IANA
Salary and career survey: Benchmarks and advice; Designing controls; Remote data collection, historians; Control valve advances; Hannover Messe; Control Engineering International
System integration: Best practices and technologies to help; Virtualization virtues; Cyber security advice; Motor system efficiency, savings; Product exclusives; Road to Hannover
This article collection contains several articles on the Industrial Internet of Things (IIoT) and how it is transforming manufacturing.
PLCs, robots, and the quest for a single controller; how OEE is key to automation solutions.

Find and connect with the most suitable service provider for your unique application. Start searching the Global System Integrator Database Now!

The digital oilfield: Utilizing Big Data can yield big savings; Virtualization a real solution; Tracking SIS performance
Getting to the bottom of subsea repairs: Older pipelines need more attention, and operators need a repair strategy; OTC preview; Offshore production difficult - and crucial
Digital oilfields: Integrated HMI/SCADA systems enable smarter data acquisition; Real-world impact of simulation; Electric actuator technology prospers in production fields
click me