Managing and monitoring plant power

The Sao Salvador Poultry Processing Plant, better known as SuperFrango (SuperChicken), is a pioneer in modern poultry-raising systems in Brazil’s central region.

10/01/2010


The Sao Salvador Poultry Processing Plant, better known as SuperFrango (SuperChicken), is a pioneer in modern poultry-raising systems in Brazil’s central region. Headquartered in Itaberai, Brazil, the plant was founded in 1970 through a partnership between friends Carlos Vieira da Cunha and Jose Carlos de Souza. SuperFrango routinely invests in new technology to improve operational stability, which was demonstrated during the recent Pintos de Corte incubator.

After 5 years of planning, design, and construction, along with a $12.6 million investment, SuperFrango opened its new slightly larger than 150,000-sq-ft facility on more than 1 million sq-ft of space. The plant provides jobs for roughly 1,400 people, processes more than 180,000 chickens daily, and produces more than 10.7 million eggs monthly. As with most industrial facilities, SuperFrango needs reliable, economical power. Utility power at the site is provided based on “time-of-day” rates, so economics dictated a design that provides a seamless transfer between utility and generator plant. A prime power generation and ramping power transfer system was the solution SuperFrango sought. SuperFrango partnered with Cummins Power Generation, and the installation began in April 2006 with a delivery made in November 2008.

The system Cummins provided included five Cummins model C400D6 456 kWA diesel generator sets driven by Cummins NTA855G5 engines. The generator sets also include alternators and PowerCommand digital paralleling controls and switchgear manufactured by Cummins. The Cummins peak power system helps SuperFrango meet its electricity needs by monitoring utility power, starting and paralleling generators when and if power fails, and transferring from the utility to generators as needed. Depending on the time of day, the system will automatically start the generators, parallel them to the utility, and control their power output to minimize load and utility costs.

The generators provided can operate the entire facility. When the time comes to shut the generators down, the system synchronizes and parallels the generators to the utility, transfers the load back to the utility, disconnects and cools the generators, and leaves them ready to start again. By operating the standby power system in prime power mode at peak hours, SuperFrango achieves savings of 30% during the 3 hours of the day when utility power costs are the highest.

Information provided by Cummins Power Generation



No comments
The Engineers' Choice Awards highlight some of the best new control, instrumentation and automation products as chosen by...
The System Integrator Giants program lists the top 100 system integrators among companies listed in CFE Media's Global System Integrator Database.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
This eGuide illustrates solutions, applications and benefits of machine vision systems.
Learn how to increase device reliability in harsh environments and decrease unplanned system downtime.
This eGuide contains a series of articles and videos that considers theoretical and practical; immediate needs and a look into the future.
Additive manufacturing advancements; Machine vision enhances robotics; Fieldbus evolution; Process safety; Advice from System Integrators of the Year; Road to IANA
Salary and career survey: Benchmarks and advice; Designing controls; Remote data collection, historians; Control valve advances; Hannover Messe; Control Engineering International
System integration: Best practices and technologies to help; Virtualization virtues; Cyber security advice; Motor system efficiency, savings; Product exclusives; Road to Hannover
This article collection contains several articles on the Industrial Internet of Things (IIoT) and how it is transforming manufacturing.
PLCs, robots, and the quest for a single controller; how OEE is key to automation solutions.

Find and connect with the most suitable service provider for your unique application. Start searching the Global System Integrator Database Now!

The digital oilfield: Utilizing Big Data can yield big savings; Virtualization a real solution; Tracking SIS performance
Getting to the bottom of subsea repairs: Older pipelines need more attention, and operators need a repair strategy; OTC preview; Offshore production difficult - and crucial
Digital oilfields: Integrated HMI/SCADA systems enable smarter data acquisition; Real-world impact of simulation; Electric actuator technology prospers in production fields
click me