Manufacturers’ tips and tricks for commissioning, balancing buildings

Two manufacturers provide insights, tools, and tips on how to commission and balance building systems.

08/28/2013


Jeff Abramson, Director of thermography development, Fluke Corp., Everett, Wash. Courtesy: FlukeJessica Frackleton, Senior manager of product marketing, Onset Computer Corp., Bourne, Mass. Courtesy: Onset Computer Corp.

Participants

  • Jeff Abramson, Director of thermography development, Fluke Corp., Everett, Wash.
  • Jessica Frackleton, Senior manager of product marketing, Onset Computer Corp., Bourne, Mass.

 

CSE: What engineering challenges do you help commissioning agents (CxAs) overcome?

Fluke: Test and measurement tools help commissioning agents collect accurate data that confirms a building’s performance meets the standards and specifications it was designed against. For ventilation commissioning, many agents use airflow meters, either a multipurpose air meter that incorporates outsides air, CO, and CO2, or a single-function micromanometer. At the register and for sensor checks, most CxAs use a humidity and temperature meter and some use a handheld infrared (IR) thermometer. For building controls system signal continuity verification, sometimes a CxA will use a mA or Volts dc loop tester. When inspecting the mechanical and electro-mechanical setup, a CxA will use electrical test tools to verify supply voltage and will use thermal imagers to verify appropriate performance under load. Thermal imagers are also used for building diagnostics to inspect the overall building envelope. When assessing the lighting system, a CxA will use a light meter to measure the lumens output compared to the lighting requirements for the task or activity anticipated for that area of the building. 

Onset: For many of our customers, access to data from building automation systems (BAS) is either difficult to obtain, not sufficient, or non-existent. Our data loggers are a low-cost, minimally intrusive way of augmenting this data to pinpoint energy savings opportunities in both new and existing building commissioning. The access to this data allows for CxAs to really engineer solutions tailored to the usage and operational characteristics of each building they enter, thereby providing building owners and operators with true, measurable savings. 

CSE: What unique challenges might engineers encounter regarding the building envelope, and how would you help overcome them?

Onset: One of the most troublesome challenges that we hear from CxAs is their inability to access data the way they want it. This problem presents itself in two critically different ways:

  1. Access to data is restricted because of limitations or programming requirements of the automation systems that are in place already
  2. The physical location of the measurement point is challenging or impossible to access.

We have helped numerous projects overcome these challenges by providing data loggers that are flexible, easy to use, and allow for data to quickly be exported to any spreadsheet program or streamed seamlessly to the Web for access anywhere. We’ve worked on many projects with our clients who desire to use a combination of loggers from our standalone to our wireless data logging networks. We often hear from customers who have a lot of success with our Web-based data logging platform because it serves as an easy-to-use, flexible data logger for collecting indoor building energy information as well as localized weather data to help normalize expected energy usage throughout the year. In many commissioning projects, the flexibility to measure what you need where you need it, and manipulate the data easily can mean the difference between a successful project that quickly pays for itself a long-running headache that never yields the returns you expect.

Fluke: Air leakage is an especially tricky problem to diagnose. Using thermal imaging can show conductive heat loss due to various problems such as missing or damaged insulation. An improperly installed or configured HVAC system could take months to diagnose based on complaints from occupants, but a properly done thermal scan on the HVAC ducting could find the root cause within a day. An active HVAC system can change the thermal patterns, so it is imperative to inspect while the system is running.


<< First < Previous 1 2 3 Next > Last >>

No comments
The Engineers' Choice Awards highlight some of the best new control, instrumentation and automation products as chosen by...
Each year, a panel of Control Engineering editors and industry expert judges select the System Integrator of the Year Award winners.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
Learn how to increase device reliability in harsh environments and decrease unplanned system downtime.
This eGuide contains a series of articles and videos that considers theoretical and practical; immediate needs and a look into the future.
Learn how to create value with re-use; gain productivity with lean automation and connectivity, and optimize panel design and construction.
Lost in the gray scale? How to get effective HMIs; Best practices: Integrate old and new wireless systems; Smart software, networks; Service provider certifications
Fixing PID: Part 2: Tweaking controller strategy; Machine safety networks; Salary survey and career advice; Smart I/O architecture; Product exclusives
Big plans for small nuclear reactors: Simpler, safer control designs; Smarter manufacturing; Industrial cloud; Mobile HMI; Controls convergence
The Ask Control Engineering blog covers all aspects of automation, including motors, drives, sensors, motion control, machine control, and embedded systems.
Look at the basics of industrial wireless technologies, wireless concepts, wireless standards, and wireless best practices with Daniel E. Capano of Diversified Technical Services Inc.
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
This is a blog from the trenches – written by engineers who are implementing and upgrading control systems every day across every industry.
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.

Find and connect with the most suitable service provider for your unique application. Start searching the Global System Integrator Database Now!

Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Control Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.