Nalco Chemical Laboratory

Existing building retrofit: Nalco Chemical Laboratory; Redding Linden Burr Inc.

08/09/2012


Project name: Nalco Chemical Laboratory

Location: Sugar Land, Texas

Firm name: Redding Linden Burr Inc.

Project type, building type: Existing building retrofit, research/lab/high-tech

Project duration: 2 years

Project completion date: April 29, 2008

Project budget for mechanical, electrical, plumbing, fire protection engineering only: $150,000

Engineering challenges

Engineering challenges faced on this laboratory conversion included: exhaust for 104 independently controlled chemical fume hoods in laboratory space; conversion of existing office space into laboratory space; and incorporating exhaust fans for chemical fume hoods.

Solutions

The engineering solutions used to resolve the three issues were as follows. The MEP system was designed to support 104 chemical fume hoods with an airflow lab tracking control system, with combination fume hood sash control to maintain proper lab pressurization control. The project converted existing office space on the second floor of a three-story structure to two chemistry laboratories with 36 fume hoods similar to the arrangement of the existing first-floor laboratory, which also has 36 fume hoods. In addition to this second- and first-floor labs, the mechanical system was sized for 18 future fume hoods in the existing training room area on the second floor, and 14 future fume hoods directly below on the first floor. The majority of the existing air handler equipment was reutilized; however, a new air handler with a capacity of 38,400 cfm needed to be included in the design to serve the exhaust requirements and additional first-floor fume hood requirements. New exhaust fans on the roof were sized to accommodate the new fume hoods on the second floor, the existing fume hoods on the first floor, and the future hoods described above. The chiller and boiler plants were modified to serve the air handling modifications and expansion to the laboratory. The exhaust fans consist of a fan assembly with five laboratory dilution fans with a total capacity of 100,000 cfm tying in all new and existing exhaust ducts to the manifold of the new fan assembly and demolishing the existing fans. The design incorporates ductwork for the future fume hoods.



No comments
The Engineers' Choice Awards highlight some of the best new control, instrumentation and automation products as chosen by...
The System Integrator Giants program lists the top 100 system integrators among companies listed in CFE Media's Global System Integrator Database.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
This eGuide illustrates solutions, applications and benefits of machine vision systems.
Learn how to increase device reliability in harsh environments and decrease unplanned system downtime.
This eGuide contains a series of articles and videos that considers theoretical and practical; immediate needs and a look into the future.
Intelligent, efficient PLC programming: Cost-saving programming languages are available now; Automation system upgrades; Help from the cloud; Improving flow control; System integration tips
Smarter machines require smarter systems; Fixing PID, part 3; Process safety; Hardware and software integration; Legalities: Integrated lean project delivery
Choosing controllers: PLCs, PACs, IPCs, DCS? What's best for your application?; Wireless trends; Design, integration; Manufacturing Day; Product Exclusive
PLCs, robots, and the quest for a single controller; how OEE is key to automation solutions.
This article collection contains several articles on improving the use of PID.
Learn how Industry 4.0 adds supply chain efficiency, optimizes pricing, improves quality, and more.

Find and connect with the most suitable service provider for your unique application. Start searching the Global System Integrator Database Now!

Special report: U.S. natural gas; LNG transport technologies evolve to meet market demand; Understanding new methane regulations; Predictive maintenance for gas pipeline compressors
Cyber security cost-efficient for industrial control systems; Extracting full value from operational data; Managing cyber security risks
Drilling for Big Data: Managing the flow of information; Big data drilldown series: Challenge and opportunity; OT to IT: Creating a circle of improvement; Industry loses best workers, again