Port of Long Beach, Middle Harbor Redevelopment

System overhaul: Port of Long Beach, Middle Harbor Redevelopment; P2S Engineering

08/09/2012


Port of Long Beach aerial viewProject name: Port of Long Beach, Middle Harbor Redevelopment

Location: Long Beach, Calif.

Firm name: P2S Engineering

Project type, building type: System overhaul, manufacturing

Project duration: 6 years

Project completion date: June 9, 2012

Project budget for mechanical, electrical, plumbing, fire protection engineering only: $70 million

Engineering challenges

The Port’s middle harbor container shipping terminals were old, outdated, and designed for a past era of containerized shipping. To improve efficiency and meet current 21st century environmental standards, they had to be updated. This would allow the Port of Long Beach not only the opportunity to utilize new technologies, but also infrastructure upgrades that would improve the environment. As a result, once completed, the power infrastructure will have the capacity to fully support not only typical terminal needs (medium-voltage quay cranes, site lighting, and building distribution), but also greener port technologies such as shore-to-ship power and electrified rail-mounted gantry cranes in the container yard.

Solutions

P2S designed a reliable distribution system to serve present and future needs for the Middle Harbor. The completed mega-terminal will be served by a 112 MVA, 66-12 kV substation that will be constructed in stages over the next 10 years. The terminal also includes a 12 kV intermodal yard substation; (3) 6.6 kV shore power substations; (10) 480 V reefer substations; site distribution to facilitate power and communications to medium-voltage quay and stacker cranes, shore power outlets, reefer outlets, terminal site lighting, and buildings; and a state-of-the-art energy and power management solution for managing the increased demands of the electrified terminal. P2S is also advancing and standardizing shore-to-ship power solutions by leading the development of an international IEC/ISO/IEEE standard for shore-to-ship power. This ensures that the shore-to-ship power system at the Middle Harbor is state-of-the-art. It will also serve as an example for other terminals nationwide to follow.

Artist rendering of Port of Long BeachArtist rendering of Port of Long Beach



No comments
The Engineers' Choice Awards highlight some of the best new control, instrumentation and automation products as chosen by...
Each year, a panel of Control Engineering editors and industry expert judges select the System Integrator of the Year Award winners.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
Learn how to increase device reliability in harsh environments and decrease unplanned system downtime.
This eGuide contains a series of articles and videos that considers theoretical and practical; immediate needs and a look into the future.
Learn how to create value with re-use; gain productivity with lean automation and connectivity, and optimize panel design and construction.
Go deep: Automation tackles offshore oil challenges; Ethernet advice; Wireless robotics; Product exclusives; Digital edition exclusives
Lost in the gray scale? How to get effective HMIs; Best practices: Integrate old and new wireless systems; Smart software, networks; Service provider certifications
Fixing PID: Part 2: Tweaking controller strategy; Machine safety networks; Salary survey and career advice; Smart I/O architecture; Product exclusives
The Ask Control Engineering blog covers all aspects of automation, including motors, drives, sensors, motion control, machine control, and embedded systems.
Look at the basics of industrial wireless technologies, wireless concepts, wireless standards, and wireless best practices with Daniel E. Capano of Diversified Technical Services Inc.
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
This is a blog from the trenches – written by engineers who are implementing and upgrading control systems every day across every industry.
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.

Find and connect with the most suitable service provider for your unique application. Start searching the Global System Integrator Database Now!

Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Control Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.