Project: Baton Rouge Wastewater Pump Station SCADA System-10/27/05

10/27/2005


October 27, 2005

The prime consultant on this project has completed a draft of a Phase I RTU and HMI request for proposal document that is being circulated with the city of Baton Rouge. This consultant also had a meeting with the Phase II installing contractor and the city, mainly to provide them a status update on the project.

We are in the process of testing a phone/PDA device running Windows Mobile 5.0 for use by maintenance personnel in receiving after-hours alarm notifications. The city currently uses a Nextel phone to get email alarm notifications. We believe we can duplicate the existing email alarm functionality plus give them the ability to have the same access to screens they would see on the local HMI. Monthly account cost is projected to be somewhat higher, but close to the cost of their existing service.

Update of the existing RTUs to Modbus-compatible firmware has been proceeding slowly, due to the spare controller being lost somewhere in shipment back to the manufacturer. Also, we have discovered that there have been undisclosed software and hardware modifications done to the first booster station to be tested. This will add to our cost since we need to replace a missing radio and battery charger cabinet (will require change order). Software changes added to this station complicate the original design which had standardized programs for the 13 booster stations into two programs - one for the 2-pump and one for the 3-pump stations.





No comments
The Engineers' Choice Awards highlight some of the best new control, instrumentation and automation products as chosen by...
The System Integrator Giants program lists the top 100 system integrators among companies listed in CFE Media's Global System Integrator Database.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
This eGuide illustrates solutions, applications and benefits of machine vision systems.
Learn how to increase device reliability in harsh environments and decrease unplanned system downtime.
This eGuide contains a series of articles and videos that considers theoretical and practical; immediate needs and a look into the future.
Sensor-to-cloud interoperability; PID and digital control efficiency; Alarm management system design; Automotive industry advances
Make Big Data and Industrial Internet of Things work for you, 2017 Engineers' Choice Finalists, Avoid control design pitfalls, Managing IIoT processes
Engineering Leaders Under 40; System integration improving packaging operation; Process sensing; PID velocity; Cybersecurity and functional safety
This article collection contains several articles on the Industrial Internet of Things (IIoT) and how it is transforming manufacturing.

Find and connect with the most suitable service provider for your unique application. Start searching the Global System Integrator Database Now!

SCADA at the junction, Managing risk through maintenance, Moving at the speed of data
Flexible offshore fire protection; Big Data's impact on operations; Bridging the skills gap; Identifying security risks
The digital oilfield: Utilizing Big Data can yield big savings; Virtualization a real solution; Tracking SIS performance
click me