In this project profile, Lonsdon Stansted Airport Engineering Team performed an existing building retrofit in order to reduce the amount of time needed for maintenance inspections.

03/20/2014


Project name: Improving Switchgear Inspections at London's Stansted Airport

Project type: Existing building retrofit

Engineering Firm: London Stansted Airport Engineering Team

Building type: Utilities/public works/transportation

Location: Stansted, Essex, United Kingdom

Timeline: Nov. 11, 2012 - Dec. 24, 2012


Thermographer inspects switchgear at Stansted Airport through an IRISS CAP infrared camera. Courtesy: London Stansted Airport

Building details

London Stansted Airport has permission to handle 35 million passengers annually and currently 17.5 million people pass through the terminal building each year. The airports electrical structure is enormous. Power is brought onto the site at 33kV and transformed down to 11V. 

Project details

At best, Stansted's engineers had four hours per night in which to conduct predictive maintenance inspections. By the time they had the system safe, the window of opportunity was reduced even more. This meant the entire inspection cycle was significantly protracted and no system could be checked under load. With the installation of IRISS CAP Series infrared inspection windows, the savings in terms of inspection time and associated costs went up dramatically. Payback was instant, but the benefits extended beyond that.

With IRISS infrared windows, Stansted Airport switchgear systems are thoroughly inspected. Courtesy: London Stansted Airport

Project success

Once the IRISS windows were installed there was an immediate impact on switchgear inspections time. It took just took five hours to complete the job in daylight hours, including walking from one substation to the next and coffee breaks. Previously, it took the engineers two nights to inspect just one panel. There is no longer a need for isolations or back feed, and the engineers' safety is completely assured. A single thermographer with a thermal imaging camera and without PPE can do everything. An initial thermal survey of the fully energized low-voltage systems that serve the main terminal block showed just two minor cable faults. For the first time, the airport had a benchmark for trending future performance and the complete assurance that everything was working optimally. This was not possible before install the IRISS CAP Series IR window.


London Stansted Airport, Enterprise House, Bassingbourn Road, Essex, United Kingdom CM24 1QW



No comments
The Engineers' Choice Awards highlight some of the best new control, instrumentation and automation products as chosen by...
The System Integrator Giants program lists the top 100 system integrators among companies listed in CFE Media's Global System Integrator Database.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
This eGuide illustrates solutions, applications and benefits of machine vision systems.
Learn how to increase device reliability in harsh environments and decrease unplanned system downtime.
This eGuide contains a series of articles and videos that considers theoretical and practical; immediate needs and a look into the future.
Salary and career survey: Benchmarks and advice; Designing controls; Remote data collection, historians; Control valve advances; Hannover Messe; Control Engineering International
System integration: Best practices and technologies to help; Virtualization virtues; Cyber security advice; Motor system efficiency, savings; Product exclusives; Road to Hannover
Collaborative robotics: How to improve safety, return on investment; Industrial Internet of Things, Industrie 4.0: World views; High-performance HMI, Information Integration: OPC and OMG
This article collection contains several articles on the Industrial Internet of Things (IIoT) and how it is transforming manufacturing.
PLCs, robots, and the quest for a single controller; how OEE is key to automation solutions.

Find and connect with the most suitable service provider for your unique application. Start searching the Global System Integrator Database Now!

Getting to the bottom of subsea repairs: Older pipelines need more attention, and operators need a repair strategy; OTC preview; Offshore production difficult - and crucial
Digital oilfields: Integrated HMI/SCADA systems enable smarter data acquisition; Real-world impact of simulation; Electric actuator technology prospers in production fields
Special report: U.S. natural gas; LNG transport technologies evolve to meet market demand; Understanding new methane regulations; Predictive maintenance for gas pipeline compressors
click me