Rendering Plant Keeps Running During Control System Upgrade

Automation integrator case study: Integrated architecture delivers needed alarm logging and reporting capabilities.

12/06/2011


An Ethernet-based network and architecture allows the rendering plant to monitor and report on its operations in real time. Courtesy: I2RA rendering plant processing million of pounds of waste animal tissue per week needed a complete control system overhaul, with no downtime. Rendering converts waste tissue into stable value-added materials.

The plant works two shifts a day, accepting shipments from multiple processing plants. The fact was the animal tissue would arrive at the door whether or not the rendering plant was running. It had nowhere else to go. What’s more, spare parts for some of the control-system components in use were no longer available; the system had no redundancy or real-time reporting; and there was only one support person, stationed at a remote location.

The project participants agree that teamwork among plant, corporate, systems integrator, and electrical subcontractor personnel helped make the project a success. The upgrade included use of a modern information architecture, positioning the plant for greater use of information technology in the immediate future.

PLC I/O panel replacement

Today’s rendering plants need a reliable architecture that includes alarm and event data logging, and that delivers reporting needed for plant optimization.

Rendering plant continues to run through a process control system upgrade. Courtesy: I2RPhysically, the existing system included two four-door panels packed with nine vintage eight-slot racks and 64 I/O cards all controlled by a single processor. Two remote panels brought the system to 77 I/O cards. The cards themselves and the wiring were “vintage” and, having served well, were due for replacement.

Dallas-based I2R, a system integrator, contracted to supply all of the PLC I/O panels, programming and design, on-site electrical contractor supervision, and on-site start-up. The upgrades were divided into five sections, each to be installed during a weekend downtime window. Each window was from noon Saturday to 9 a.m. Monday morning—just 45 hours. The project manager was to conduct weekly conference calls with corporate and plant personnel.

It wasn’t possible to start by removing the old panels and installing the new ones. Instead, a nearby lab room was used to house the new panels, with pull boxes installed above them so that new wiring could be run to the plant floor from the panels. The technology employed included the following:

  • Schneider Modicon Quantum fully redundant central processing units (CPU)
  • Uninterruptible power supply (UPS) backup for each processor
  • Wonderware ArchestrA system platform
  • Redundant servers and network switches

I2R held a factory acceptance test four weeks prior to start-up and a software simulation three weeks prior. Operators and supervisors were able to interact with the system and ask questions, eliminating surprises and saving time.

Workflow for rendering begins outside the plant. Courtesy: I2RNew wiring and conduit were run while the plant was running. New conduit and single-conductor wiring replaced cable tray with tray cable. Once the new system was online, the old tray and tray cable were removed.

“The teamwork couldn’t have been better,” said the I2R project manager. “The plant worked very hard to give us the biggest downtime window they could. The contractors and software team were ready.”

Six start-up weekends had been planned, but that number was reduced to five because of the preparation work of the plant and contractor in prebuilding and testing motor control center (MCC) buckets. “The plant made the buckets available, saving time and money because the rebuilds were done on straight time rather than overtime,” the project manager said.

The upgrade has improved operations at the rendering plant, which has experienced no unplanned downtime in the three months following work completion. Remote support is online and development of business-intelligence dashboards is being planned.

Jerry Smith is president, Integrity Integration Resources (I2R), A Cates Company.

www.i2r.com  

www.wonderware.com 

www.modicon.com 



No comments
The Engineers' Choice Awards highlight some of the best new control, instrumentation and automation products as chosen by...
The System Integrator Giants program lists the top 100 system integrators among companies listed in CFE Media's Global System Integrator Database.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
This eGuide illustrates solutions, applications and benefits of machine vision systems.
Learn how to increase device reliability in harsh environments and decrease unplanned system downtime.
This eGuide contains a series of articles and videos that considers theoretical and practical; immediate needs and a look into the future.
System integration: Best practices and technologies to help; Virtualization virtues; Cyber security advice; Motor system efficiency, savings; Product exclusives; Road to Hannover
Collaborative robotics: How to improve safety, return on investment; Industrial Internet of Things, Industrie 4.0: World views; High-performance HMI, Information Integration: OPC and OMG
9 tips: How to integrate a servo system; Process control mathematical models; Serial network grounding; Engineers' Choice Awards; Learn from cyber security mistakes
This article collection contains several articles on the Industrial Internet of Things (IIoT) and how it is transforming manufacturing.
PLCs, robots, and the quest for a single controller; how OEE is key to automation solutions.
Learn how Industry 4.0 adds supply chain efficiency, optimizes pricing, improves quality, and more.

Find and connect with the most suitable service provider for your unique application. Start searching the Global System Integrator Database Now!

Getting to the bottom of subsea repairs: Older pipelines need more attention, and operators need a repair strategy; OTC preview; Offshore production difficult - and crucial
Digital oilfields: Integrated HMI/SCADA systems enable smarter data acquisition; Real-world impact of simulation; Electric actuator technology prospers in production fields
Special report: U.S. natural gas; LNG transport technologies evolve to meet market demand; Understanding new methane regulations; Predictive maintenance for gas pipeline compressors

(copy 5)

click me