The best changeover is no changeover

Achieving effective changeovers should start with eliminating those that are unnecessary.

10/01/2012


In a perfect manufacturing world, one would be able to dedicate production assets to one product, run that product continuously, and never, ever be forced to change to another product. If one could do so, this mode of operation would yield true world-class performance. Think of it—no constant struggle to reduce the losses that invariably occur as part of the changeover process.  

Unfortunately, for most of us a perfect world doesn’t exist. Our markets are highly volatile, demand fluctuates, and inventory cost is too high to support dedicated production assets. Instead, we must be flexible and capable of running multiple products on one or more assets. We must do changeovers, but that does not mean that we must sustain unnecessary downtime and capacity losses.

While some changeovers are necessary, most plants make far too many. In a typical plant, it is not unusual to see production assets average two or more changeovers a day, often switching between fewer than three products. Just last week, I observed one asset change from one product to another, back to the first product, and then back to the second in a 24-hour period.

Achieving effective changeovers should start with eliminating those that are unnecessary. In a typical plant, at least half of the changeovers could be eliminated by adhering to standard products and effective production planning. When one evaluates the forcing functions that drive changeovers, two are dominant. The first is the number of orders received for nonstandard products or delivery schedules.

Too often the sales group commits the plant to orders that force production to react—often without standard procedures for producing the nonstandard product.

The second dominant forcing function is deficiencies in the production planning process. In too many instances, production planning—really scheduling—is little better than a clerical function. Little, if any, effort is placed on effective asset utilization, conversion cost, or the level of effort required to changeover. Instead, the activity is limited to plugging each order into the first apparent hole in the schedule without regard to impact on performance.

Effective production planning and scheduling are essential to sustainable best-in-class performance and the best means of eliminating the negative impact of changeovers. Always remember that the best changeover is no changeover at all, and that can only be achieved through effective planning.

Once all unnecessary changeovers have been eliminated, we must also improve how required changeovers are performed. There are seven steps that are integral to effective changeovers:

  1. Separate internal from external setup operations. External operations can be done without stopping the asset or production line or interfering with normal production. These tasks can be completed before shutting down for the changeover.

  2. Convert internal to external setup. Every effort should be made to convert as much of the changeover process as possible to external tasks. Every task that can be performed before shutdown extends the production and its resultant capacity.

  3. Create standard work, not generic functions or tasks. Standard work is the keystone of best-in-class performance—including changeovers. Leave nothing to chance. Implement step-by-step task descriptions, roles, and responsibilities that clearly define the changeover process. Train all involved and then enforce absolute adherence; compliance cannot be optional.

  4. Use functional clamps or eliminate fasteners altogether. Traditional fasteners are inefficient, require too much time to loosen and tighten, and introduce a significant risk of mistakes that too often result in difficult, prolonged start-ups. Every effort should be made to replace traditional fasteners with quick-lock clamps or fasteners. Effective use of functional clamps will reduce changeover time as well as eliminate mistakes.

  5. Use intermediate jigs and fixtures. The use of jigs and fixtures to assure consistent, repeatable setups is essential. A jig and fixture set should be created for each product type that will be produced and permanently located adjacent to the appropriate asset. 

  6. Adopt parallel operations. To the extent possible, eliminate all serial operations or tasks. Safety cannot be compromised, but many shutdown, changeover, and start-up tasks can be performed simultaneously, thereby eliminating lost time as well as wasted motion.

  7. Eliminate adjustments. The extended need to make adjustments, especially during the start-up process, is perhaps the greatest source of scrap and lost production in the entire changeover process. Much of this need can be eliminated by standard work, jigs, fixtures, and mistake-proofing the changeover process.

The losses associated with changeovers range from 5% to 25% of total available production hours, and many can be eliminated. Elimination is not easy; it requires discipline and a coordinated, combined effort that includes sales, production planning, logistics, and all other functional groups. It’s not easy, but it can be done—if you are willing to do it.



No comments
The Engineers' Choice Awards highlight some of the best new control, instrumentation and automation products as chosen by...
Each year, a panel of Control Engineering editors and industry expert judges select the System Integrator of the Year Award winners.
Control Engineering Leaders Under 40 identifies and gives recognition to young engineers who...
Learn more about methods used to ensure that the integration between the safety system and the process control...
Adding industrial toughness and reliability to Ethernet eGuide
Technological advances like multiple-in-multiple-out (MIMO) transmitting and receiving
Virtualization advice: 4 ways splitting servers can help manufacturing; Efficient motion controls; Fill the brain drain; Learn from the HART Plant of the Year
Two sides to process safety: Combining human and technical factors in your program; Preparing HMI graphics for migrations; Mechatronics and safety; Engineers' Choice Awards
Detecting security breaches: Forensic invenstigations depend on knowing your networks inside and out; Wireless workers; Opening robotic control; Product exclusive: Robust encoders
The Ask Control Engineering blog covers all aspects of automation, including motors, drives, sensors, motion control, machine control, and embedded systems.
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
News and comments from Control Engineering process industries editor, Peter Welander.
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.
This is a blog from the trenches – written by engineers who are implementing and upgrading control systems every day across every industry.
Anthony Baker is a fictitious aggregation of experts from Callisto Integration, providing manufacturing consulting and systems integration.
Integrator Guide

Integrator Guide

Search the online Automation Integrator Guide
 

Create New Listing

Visit the System Integrators page to view past winners of Control Engineering's System Integrator of the Year Award and learn how to enter the competition. You will also find more information on system integrators and Control System Integrators Association.

Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Control Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.