Time, material savings mean cost savings

Below is an example of how saving time and money on materials can translate to overall savings when wiring wire motor starters, contactors, and pilot devices.

08/13/2013


Many people say, “Time is money.” However, material is too. When it comes to engineering, assembling, and testing control panels, reducing either time or materials (or both) can reduce costs significantly. Here are two examples that illustrate how reducing time and materials can also reduce costs. 

In the time reduction example, the estimated time to wire motor starters, contactors, and pilot devices is 4 hours and 29 minutes. However, the estimate is only 41 minutes if a device-level wiring system is used—an 85% reduction in wiring time. Engineering and testing times were also reduced.

Courtesy: Eaton

In the material reduction example, an installation that consisted of 1,600 motor starters would have required 7.83 miles of control wiring. However, by using a device-level wiring system, only 0.45 mile of flat cable was used. Calculating the material cost of each method using $0.61/ft for flat cable and $0.14 for #14 AWG, the device-level wiring system saved more than $4,300. In addition, the calculated savings for wiring/assembly time was 22 man-days.

Courtesy: Eaton

Another significant benefit is the device-level wiring network allowed the system to be installed and commissioned without having to ring out a multitude of control wiring connections. This type of control system can also connect electronic motor starters to the system, which allows motor current and other loads to be monitored without having to add current transformers or analog input cards to the PLC. This feature could enable a higher level of predictive data monitoring that was prohibitively expensive in the past.

This article appears in the Applied Automation supplement for Control Engineering and Plant Engineering



No comments
The Engineers' Choice Awards highlight some of the best new control, instrumentation and automation products as chosen by...
Each year, a panel of Control Engineering editors and industry expert judges select the System Integrator of the Year Award winners.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
Learn how to increase device reliability in harsh environments and decrease unplanned system downtime.
This eGuide contains a series of articles and videos that considers theoretical and practical; immediate needs and a look into the future.
Learn how to create value with re-use; gain productivity with lean automation and connectivity, and optimize panel design and construction.
Go deep: Automation tackles offshore oil challenges; Ethernet advice; Wireless robotics; Product exclusives; Digital edition exclusives
Lost in the gray scale? How to get effective HMIs; Best practices: Integrate old and new wireless systems; Smart software, networks; Service provider certifications
Fixing PID: Part 2: Tweaking controller strategy; Machine safety networks; Salary survey and career advice; Smart I/O architecture; Product exclusives
The Ask Control Engineering blog covers all aspects of automation, including motors, drives, sensors, motion control, machine control, and embedded systems.
Look at the basics of industrial wireless technologies, wireless concepts, wireless standards, and wireless best practices with Daniel E. Capano of Diversified Technical Services Inc.
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
This is a blog from the trenches – written by engineers who are implementing and upgrading control systems every day across every industry.
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.

Find and connect with the most suitable service provider for your unique application. Start searching the Global System Integrator Database Now!

Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Control Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.