Top Plant 2012: Pfizer Global Supply
Jack Smith
In 2008, Michigan OSHA recognized the facility as a Michigan Voluntary Protection Program (MVPP) STAR Site with a recertification in 2011. The Kalamazoo plant is the state’s largest facility and one of only 32 sites in the state to hold the certification. “We actually invited Michigan OSHA to inspect the plant and review our programs,” said Ronald Walko, senior manager, safety and industrial hygiene. “They sent two people to look at our chemical process safety program—that was the first step. If we didn’t pass those inspections, they wouldn’t have gone any further.”
During the next visit, Michigan OSHA sent seven inspectors for two weeks. “It was incredibly extensive.” Walko said. “They looked at our safety culture and Safety and Health Management System for such elements as management commitment, hazard prevention, colleague engagement, and how we do risk analysis in the plant. They assessed what kind of controls we have in place, and the PPE we use. They also looked at our training programs and verified our training records.
Michigan OSHA conducted one-on-one interviews with 138 employees and contractors to confirm that the plant’s safety programs and safety culture were in place and working. “And it was all done at random,” said Walko. “We didn’t get to pick who was interviewed. They randomly picked people from all shifts.”
The plant is eligible for recertification every three years. “It really is very meaningful to all of our colleagues,” Walko said. “The MVPP STAR certification is something that we’re really proud of because, to put it into Michigan OSHA’s terms, we are among the ‘Best of the Best.’”
Integrator Guide
| Search the online Automation Integrator Guide |
|
|
|
|
Visit the System Integrators page to view past winners of Control Engineering's System Integrator of the Year Award and learn how to enter the competition. You will also find more information on system integrators and Control System Integrators Association.
Case Study Database
Get more exposure for your case study by uploading it to the Control Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.
These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.
Click here to visit the Case Study Database and upload your case study.