University of Texas Tower Air Handling Unit Replacement

System overhaul: University of Texas Tower Air Handling Unit Replacement; EEA Consulting Engineers

08/09/2012


The University of Texas at Austin main building (the U.T. Tower) is shown during installation of the new air-handling unit. Courtesy: Flintco, the general contractor on the project. (Click to enlarge)Project name: University of Texas Tower Air Handling Unit Replacement

Location: Austin, Texas

Firm name: EEA Consulting Engineers

Project type, building type: System overhaul, school (college, university)

Project duration: 1.5 years

Project completion date: April 30, 2007

Project budget for mechanical, electrical, plumbing, fire protection engineering only: $77,000

Engineering challenges

Location and space constraints for the new equipment: The tower was occupied and existing equipment remained in use for duration of the project. There was limited access to the area where existing and new equipment were located. This area is near the top of the tower, behind the walls that support the clock facings.

Time constraint for the switch over to the new system: The two-week Christmas break between the fall and spring semesters provided the only period that the tower was not occupied. The transition from the old air handling unit to the new one was scheduled for that period, which meant that all aspects of the project absolutely had to be completed and become fully operational during the break.

Solutions

Location and space constraints for the new equipment: The solution was to remove a portion of the wall below the north clock facing to allow access. A new equipment platform and stair system was constructed to support and access the new equipment in the tall void space inside the top of the tower. A crane was used to lift the equipment and material into place as well as to remove and replace the 2,700-lb wall stones.

Time constraint for the switch over to the new system: This entailed close coordination between EEA, the owner, the subconsultants, and the contractor. All parties committed early in the project to meet deadlines and to quickly address any issues that might arise. As a result, the switch over proceeded smoothly and the tower reopened as scheduled. Following the switch, final installation was completed.



No comments
The Engineers' Choice Awards highlight some of the best new control, instrumentation and automation products as chosen by...
Each year, a panel of Control Engineering editors and industry expert judges select the System Integrator of the Year Award winners.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
Learn how to increase device reliability in harsh environments and decrease unplanned system downtime.
This eGuide contains a series of articles and videos that considers theoretical and practical; immediate needs and a look into the future.
Learn how to create value with re-use; gain productivity with lean automation and connectivity, and optimize panel design and construction.
Go deep: Automation tackles offshore oil challenges; Ethernet advice; Wireless robotics; Product exclusives; Digital edition exclusives
Lost in the gray scale? How to get effective HMIs; Best practices: Integrate old and new wireless systems; Smart software, networks; Service provider certifications
Fixing PID: Part 2: Tweaking controller strategy; Machine safety networks; Salary survey and career advice; Smart I/O architecture; Product exclusives
The Ask Control Engineering blog covers all aspects of automation, including motors, drives, sensors, motion control, machine control, and embedded systems.
Look at the basics of industrial wireless technologies, wireless concepts, wireless standards, and wireless best practices with Daniel E. Capano of Diversified Technical Services Inc.
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
This is a blog from the trenches – written by engineers who are implementing and upgrading control systems every day across every industry.
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.

Find and connect with the most suitable service provider for your unique application. Start searching the Global System Integrator Database Now!

Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Control Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.