Using BAS for M&V

03/26/2014


M&V codes and standards

For new construction projects, a number of codes and standards are emerging to drive the process. One of the most common guides driving an M&V process is LEED, which includes general requirements for trend analysis to verify performance as a part of the Energy and Atmosphere credit. Under EA Credit 5 for new construction projects, LEED offers a credit for developing and implementing a full-fledged M&V plan.

In addition to LEED, building codes in a number of jurisdictions are beginning to adopt Cx requirements that include M&V elements. The Seattle and Washington State Energy Codes are examples, in addition to Title 24 in California. In fact, the latest edition of Title 24, which will be effective in mid-2014, will drive new construction Cx processes toward requirements that are very similar to the requirements for LEED fundamental and enhanced Cx.

In contrast, M&V in existing building Cx processes tends to be driven either by the owner or the requirements of a utility incentive program that is funding the project, as mentioned previously. For example, the University of California/California State University/Investor Owned Utility (UC/CSU/IOU) MBCx program generally requires two different forms of M&V:

  1. For the initial RCx phase, energy savings incentives are based on the difference between a whole building meter consumption baseline, which is established prior to implementation, and the baseline that exists at the whole building meter after implementation.
  2. For energy conservation measures implemented subsequent to the initial RCx effort, the savings are incented based on engineering calculations. However, the validity of the calculation is frequently verified using M&V strategies, either at the whole building level or at the system level.

Regardless of the Cx process, most M&V standards and code requirements trace their roots to the International Performance Measurement and Verification Protocol (IPMVP). This standard sets rigorous requirements regarding the protocols, methodology, and tools used to quantify resource savings. In general, and with regard to M&V methodologies, IPMVP suggests four options for determining savings, including retrofit isolation by measuring certain key parameters, retrofit isolation by measuring all parameters, whole facility energy measurement, and calibrated simulation.

M&V plans

During a RCx project, depending on owner project requirements (OPR), input from the operation and maintenance (O&M) team during interviews, and the RCx agent site visits and reviews, a set of goals will be introduced as part of an M&V plan draft. This draft will be reviewed by the owner’s team and finalized. This document will define the extent of M&V. In general, a RCx M&V plan includes the following:

  • The timing to put the RCx contract in place
  • Potential preparations prior to each site visit
  • Site visit timing and requirements
  • Identification of systems (should be included in the RCx project and are part of the M&V plan)
  • Assessment of BAS and control points for each system to identify control points that should be trended
  • Identification of tools (direct and/or indirect monitoring) for launching the trending process
  • Data analysis schedule
  • Development of energy and water saving measures and O&M opportunities
  • Quantification of energy and water saving measures
  • Writing a draft report, owner’s review, final report issuance, and presentation.


No comments
The Engineers' Choice Awards highlight some of the best new control, instrumentation and automation products as chosen by...
Each year, a panel of Control Engineering editors and industry expert judges select the System Integrator of the Year Award winners.
The Engineering Leaders Under 40 program identifies and gives recognition to young engineers who...
Learn how to increase device reliability in harsh environments and decrease unplanned system downtime.
This eGuide contains a series of articles and videos that considers theoretical and practical; immediate needs and a look into the future.
Learn how to create value with re-use; gain productivity with lean automation and connectivity, and optimize panel design and construction.
Go deep: Automation tackles offshore oil challenges; Ethernet advice; Wireless robotics; Product exclusives; Digital edition exclusives
Lost in the gray scale? How to get effective HMIs; Best practices: Integrate old and new wireless systems; Smart software, networks; Service provider certifications
Fixing PID: Part 2: Tweaking controller strategy; Machine safety networks; Salary survey and career advice; Smart I/O architecture; Product exclusives
The Ask Control Engineering blog covers all aspects of automation, including motors, drives, sensors, motion control, machine control, and embedded systems.
Look at the basics of industrial wireless technologies, wireless concepts, wireless standards, and wireless best practices with Daniel E. Capano of Diversified Technical Services Inc.
Join this ongoing discussion of machine guarding topics, including solutions assessments, regulatory compliance, gap analysis...
This is a blog from the trenches – written by engineers who are implementing and upgrading control systems every day across every industry.
IMS Research, recently acquired by IHS Inc., is a leading independent supplier of market research and consultancy to the global electronics industry.

Find and connect with the most suitable service provider for your unique application. Start searching the Global System Integrator Database Now!

Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Control Engineering case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.