Project: Baton Rouge Wastewater Pump Station SCADA System (April 5, 2006)

By Control Engineering Staff April 6, 2006

April 5, 2006

Some progress–April 10th has been set for a graphics review meeting. This is to confirm acceptance of the SCADA screens and layout for the first booster station, which is required before we proceed with cutover of the remaining 12 stations.

The Phase II contract has some issues that were pointed out earlier by the end user. Essentially, a number of items they say they originally asked for in the design didn’t make it into the Phase II contract bid documents. We reminded them again last week that these issues remain to be resolved, and they will need to take action on their end to resolve them–we can’t do it for them.

Our concern is that we can do a hundred percent fabulous job providing what was requested, yet still have a less-than-satisfied end user.