Project: Baton Rouge Wastewater Pump Station SCADA System (September 5, 2006)

By Control Engineering Staff September 6, 2006

Engineering staff has continued working on the sample submittal for the remaining 38 stations , as well as the help screens and a reporting format . However, we are limited by the fact that we are still waiting on the city’s reporting requirements from the prime consultants.

We have had two internal reviews of the graphics and tentative internal approval to look into a W eb – based reporting format accessible directly from the control screens.

We are continuing the periodic monitoring of data usage on all of the modems. At this time , it appears that we have good control over all of the data usage.