How to Develop a Project Execution Plan

A trend in major upstream oil & gas projects is the addition of an advanced operator training simulator (OTS). To fully realize the benefits from this technology, the OTS should be developed early enough to complete operator training before facility startup and to support process and operability studies. See diagrams, charts.

12/01/2009


AT A GLANCE
 
  • Plan ahead

  • Develop consensus early

  • Validate at agreed-upon points in the process

Sidebars:
Acronym help for engineering project management

A trend in major upstream oil & gas projects is the addition of an advanced operator training simulator (OTS). To fully realize the benefits from this technology, the OTS should be developed early enough to complete operator training before facility startup and to support process and operability studies. But there are challenges to early development, particularly when designing and implementing such advanced engineering projects. A detailed project execution plan is essential.

A high fidelity OTS is typically integrated with the same process automation system (PAS) hardware and software used to control the new facility. PAS implementation must therefore be completed sooner, often significantly sooner, than what is required to meet facility engineering and construction schedules. Consequently, the OTS schedule may drive the PAS development schedule with its cascading impact on EPC (engineering procurement construction) schedules. Project success is therefore dependent on the EPC and main automation contractor (MAC) as key stakeholders.

 

Roles and risks associated with OTS stakeholder interactions should be addressed early in the project.
Roles and risks associated with OTS stakeholder interactions should be addressed early in the project.

Understanding the elements of a project execution plan from the EPC and MAC perspectives can lessen project challenges and help clearly define the role of the client. Elements include:

  • Statement of goals;

  • Scope of work;

  • Roles and responsibility matrix;

  • Technical specifications;

  • Contracting plan;

  • Organization chart; and

  • Integrated schedule.

Here we’ll go into each of these in detail.

OTS project goals

Statement of goals should define the training and engineering study requirements, which may include:

  • Pre-startup training and familiarization for new or experienced operators;

  • Long-term training or formal re-certification of operators as may be required in some regions;

  • Process design validation and throughput optimization studies (new facility and changes);

  • Validate basic process controls and safety interlocks (new facility and changes);

  • Validate standard operating procedures (SOP) and changes; and

  • Validate PAS alarm system performance (alarm floods, alarm masking).

 

Interaction between the client and OTS provider project managers and EPC and MAC interface coordinators is significant.
Interaction between the client and OTS provider project managers and EPC and MAC interface coordinators is significant.

The statement should define the modeled facilities (new or existing facility or process units), identify key schedule milestones and provide an initial OTS lifecycle plan. The life-cycle plan, covering pre- and post-facility startup, identifies the source of project and long-term support funding and the OTS location, owner and system manager at each phase. A long-term support and software management plan also should be included.

Specifications define technical, equipment, and study requirements. The contracting strategy should recognize the unique challenges of the project. A single OTS provider should be employed to reduce interfaces, improve support, reduce schedule risk, and standardize on OTS software. The cumulative costs from all contractors should be considered when selecting the strategy. The OTS execution plan must to be prepared early to make it available when the client’s project team is ready to issue proposal requests and contracts to the EPC(s) and MAC. Vendors and contractors should be limited to those with proven technical and execution track records. Risks associated with stakeholder interfaces and accelerated schedules should be addressed early in the project through the process of risk minimization.

Scope definition

During scope definition, the client defines the equipment and processes to be modeled and the model fidelity requirements. For oil & gas applications, modeled areas typically include all major oil, gas and subsea production and utility systems. Model fidelity is typically high (

Upstream projects also commonly employ skid-mounted packaged equipment supplied with local embedded control systems provided for compression, subsea, well injection and export systems. This software is also interfaced to OTS models. MAC support may be needed to complete the PAS-OTS interface. This support can be a challenge, since peak OTS support often occurs during peak PAS activity periods.

Early OTS development may be required to support process and design validation studies. Studies may include validating facility throughput, operability and PAS display and controls performance.

OTS boundaries should be clearly delineated and stakeholder responsibilities clearly defined. Table 1 is an example of a roles and responsibilities matrix. The OTS support plan, pre- and post-delivery, is fully developed here so costs can be assessed and resources and responsibilities defined.

Schedule development

Developing an integrated schedule begins with the client defining when the OTS must be ready to start operator training and, if applicable, to support OTS studies. Then, the OTS provider, EPC and MAC each identifies when required information and equipment is needed and when deliverables can be provided. The client works with all parties to facilitate a mutually agreed schedule. Schedule risks are shared among parties.

Example timing for EPC, MAC and third-party deliverables is listed in Table 2. Example timing for OTS deliverables are listed in Table 3. OTS schedule requirements must be included in the main facility project schedule developed during front-end engineering design (FEED). Adding this and the associated new scope to the EPC and MAC schedules after contracts are signed becomes increasingly difficult, and decreases the likelihood of project success.

Schedule acceleration is typically required to meet agreed delivery dates. Common acceleration approaches include working tasks in parallel, and starting OTS and PAS development work before design documents are available. Both approaches result in varying degrees of rework, increasing the EPC’s and MAC’s scope and therefore cost. Delivering the PAS design six months sooner than is needed to meet the general facility engineering and construction schedule can trigger significant acceleration costs. Controlling these costs is a challenge for all parties.

Project realities that can impact the OTS schedule and completion include:

  • Late supply of vendor data and interface requirements;

  • Late access to vendor software needed for PAS interface development, testing and OTS integration;

  • Effectiveness and timeliness of contractor-to-contractor interfaces;

  • Client requirements trigger a major effort to develop new HMI and control software templates and standards;

  • Significant changes in the PAS design basis or scope during the detailed design phase;

  • Project adds new work processes or design requirements (for example, IEC 61511 adds steps that can lengthen the safety system design and software development duration); and

  • Unplanned custom emulations are needed, such as when vendors will not provide proprietary software or algorithms.

Organizational considerations

Project success requires sound organizational and staffing decisions. Selecting the right person for the client project manager role is critical. Recommended skills include basic contract management, an understanding of interface and schedule management, good organization and communication skills and sufficient technical knowledge and authority to respond to queries and make timely decisions. The EPC and MAC should provide an OTS interface coordinator to manage information exchange requests, attend interface meetings and coordinate schedules and activities within their respective organizations.

Risks associated with OTS stakeholder interfaces should be addressed early in the project. The “Example interfaces” illustration (on p. 9) shows some possibilities. The client is typically at the center of this challenging, multi-organization, interface-intensive effort. Employing the right people in key roles provides a means to improve the timeliness and effectiveness of an interface. Opportunities to simplify or streamline an interface also should be considered to reduce project risk.

Feedback, acceptance tests

Feedback from OTS studies will generate PAS and facility design changes to consider. The client will need a process to manage this work and its potential impact on cost and schedule. A rigorous management of change process must be in place. The change process must include review, approval, implement, test, and document work status as it progresses.

Dividing PAS acceptance tests into multiple test periods to support staged software deliveries can increase PAS scope and cost. Frequent changes and incremental testing provides the opportunity for software errors to creep in. Both should be addressed in the MAC’s change management and quality plans.

The client may need to exercise corporate agreements to ensure third-party vendors release proprietary software, algorithms or functional design information to the OTS provider.

SOP’s may need to be written earlier to allow time for verification using the OTS.

A challenge when designing safety systems to IEC 61511 is acquiring process response times for a new facility. This data is used to set safety interlock speed of response requirements. Response data from the OTS may prove to be more accurate than data derived through other means and should be explored.

Plan, realities, requirements

Early supply of a high fidelity and PAS-integrated OTS is possible, but requires the right execution plan and aggressive plan execution by all parties. The client OTS project manager and EPC and MAC coordinators are key positions that directly impact project success. Risks should be identified, managed and, to the extent possible, thoughtfully distributed among OTS contributors. How early the OTS can be delivered depends on project specific realities and requirements.

Table 1- Roles and responsibility matrix

Index Activity Owner EPC MAC OTS provider
R- Responsible, A– Approve, C – Consult, I – Inform
Phase 2– Concept phase
1Define OTS statement of goalsR
Phase 3– Front end engineering design (FEED) phase
2Develop OTS specificationARC
3Define engineering study requirementsRCCC
4Develop initial OTS execution plan & scheduleA/RR/CC
5Define OTS Scope in EPC & MAC ContractsRCCC
6Develop OTS cost estimate for OTS equipment and provider servicesRC
7Develop cost Estimate for PAS Equipment and Support Services (EPC, MAC)ARRC
Phase 4– Detailed design, procurement & implementation
8OTS procurement / contractingRCCC
9OTS kickoff meetingRIII
10Develop integrated scheduleRCCC
11Update in-house execution plans with agreed OTS milestone datesARRR
12Provide facility engineering & process dataIRII
13Provide packaged equipment control system software & dataIRII
14Provide PAS equipment & software to OTS providerARC
15Model developmentCIR
16Develop facility standard operating procedures (SOPs)RCCI
17Conduct OTS studiesICCR
18Assess/authorize OTS study-initiated changes impacting EPC and MAC.RCCI
19OTS-PAS Integration & TestingACR
20Implement OTS study-initiated & approve changes to facility and PAS designsARRI
21Train OTS trainersR
22Train operators, verify SOPsR/AC/RCC
Phase 5– Operations & maintenance phase
23Long term OTS management & supportRCC


Table 2– Example timing for EPC and MAC deliverables

EPC & MAC deliverables Deliverable status Months from start of detailed design phase
PAS hardware & base software selectedDefined in FEED
P&ID, process & equipment dataPreliminary3-10
P&ID, process & equipment dataApproved for design (AFD)6-12
Safety logic drawings and control narrativesAFD* 6-10
* Up to 22 months if dependant on packaged equipment data
Vendor data from long lead 3rd party package & equipment vendorsAFD**13-22
** Earlier dates may be required to meet OTS schedule
Issue PAS configured I/O, basic controls and HMI.Fully tested/approved software templates15-18
Spot test base HMI and controls software
Issue PAS complex controls & software updateFull factory acceptance tested (FAT)16-22
Integration to control system software from long lead, 3rd party vendorsFAT16-24
Issue PAS balance of plant softwareFAT22-28
Provide PAS equipment and applications supportAs neededDuration


Table 3– Example OTS timeline

Event or EPC and MAC supplied engineering data OTS provider activity Months from first oil
OTS award30
P&ID, process and equipment data– preliminaryPlanning, specifications29
Model build28
Model validation, FEED studies26
P&IDs, process and equipment data– AFDDetailed engineering data for model update23
Engineering studies21
Model update17
PAS deliveryPAS integration16

PAS Integration and SOP checkout, PAS studies

 
14
OTS design & integration completedOTS acceptance test8
Instructor training7
Operator training6
First oil0

 

 

From the 2009 edition of the Automation Integrator Guide, a supplement to Control Engineering magazine. www.controleng.com This annual print guide to nearly 1,800 automation system integrators is searchable online at www.controleng.com/integrators .

Read other articles in the 2010 Automation Integrator Guide .



Author Information
Author: Tom Shephard, PMP, CAP, Mustang Engineering, is a main automation contractor program manager and automation project manager.


Acronym help for engineering project management

AFD : approved for design

EPC : engineering procurement construction

FAT : factory acceptance test

FEED : front end engineering design

HMI : human-machine interface

IEC : International Electrotechnical Commission

MAC : main automation contractor

OTS : operator training simulator

P&ID : process and instrumentation diagram

PAS : process automation system

SOP : standard operating procedures



Engineers' Choice Awards
The Engineers' Choice Awards highlight some of the best new control, instrumentation and automation products as chosen by Control Engineering subscribers.
System Integrator Giants
The System Integrator Giants program lists the top 100 system integrators among companies listed in CFE Media's Global System Integrator Database.
System Integrator of the Year
Each year, a panel of Control Engineering and Plant Engineering editors and industry expert judges select the System Integrator of the Year Award winners in three categories.
How to Maximize Factory Automation Efficiency with Low Cost Machine Vision
This eGuide illustrates solutions, applications and benefits of machine vision systems.
Wireless Reliability in Harsh Environments
Learn how to increase device reliability in harsh environments and decrease unplanned system downtime.
Human Factors and the Impact on Plant Safety
This eGuide contains a series of articles and videos that considers theoretical and practical; immediate needs and a look into the future.
June 2018
Discrete and process sensor fundamentals, autotuning controls, system integrator roundtable
May 2018
Salary and Career Survey, IT and OT convergence, robotic standards and safety, secure circuit protection
April 2018
Cybersecurity best practices, artificial intelligence, robotic additive manufacturing, embedded systems, IIoT integration, energy efficiency
Edge Computing
This article collection contains several articles on how today's technologies heap benefits onto an edge-computing architecture such as faster computing, better networking, more memory, smarter analytics, cloud-based intelligence, and lower costs.
IIoT: Machines, Equipment, & Asset Management
Articles in this digital report highlight technologies that enable Industrial Internet of Things, IIoT-related products and strategies.
PLCs
Programmable logic controllers (PLCs) represent the logic (decision) part of the control loop of sense, decide, and actuate. Featured articles in this digital report compare PLCs and programmable automation controllers (PACs), industrial PCs, and robotic controllers.
SIDB

Find and connect with the most suitable service provider for your unique application. Start searching the Global System Integrator Database Now!

June 2018
Machine learning, produced water benefits, progressive cavity pumps
April 2018
ROVs, rigs, and the real time; wellsite valve manifolds; AI on a chip; analytics use for pipelines
February 2018
Focus on power systems, process safety, electrical and power systems, edge computing in the oil & gas industry
John O. Ayuk, PE, CFSE, PMP, CAP
Automation Engineer; Wood Group
Doug Baker
System Integrator; Cross Integrated Systems Group
Jose S. Vasquez, Jr.
Jose S. Vasquez, Jr.
Fire & Life Safety Engineer; Technip USA Inc.
Data Centers: Impacts of Climate and Cooling Technology
This course focuses on climate analysis, appropriateness of cooling system selection, and combining cooling systems.
Safety First: Arc Flash 101
This course will help identify and reveal electrical hazards and identify the solutions to implementing and maintaining a safe work environment.
Critical Power: Hospital Electrical Systems
This course explains how maintaining power and communication systems through emergency power-generation systems is critical.
Engineers' Choice Awards
The Engineers' Choice Awards highlight some of the best new control, instrumentation and automation products as chosen by Control Engineering subscribers.
System Integrator Giants
The System Integrator Giants program lists the top 100 system integrators among companies listed in CFE Media's Global System Integrator Database.
System Integrator of the Year
Each year, a panel of Control Engineering and Plant Engineering editors and industry expert judges select the System Integrator of the Year Award winners in three categories.
How to Maximize Factory Automation Efficiency with Low Cost Machine Vision
This eGuide illustrates solutions, applications and benefits of machine vision systems.
Wireless Reliability in Harsh Environments
Learn how to increase device reliability in harsh environments and decrease unplanned system downtime.
Human Factors and the Impact on Plant Safety
This eGuide contains a series of articles and videos that considers theoretical and practical; immediate needs and a look into the future.
June 2018
Discrete and process sensor fundamentals, autotuning controls, system integrator roundtable
May 2018
Salary and Career Survey, IT and OT convergence, robotic standards and safety, secure circuit protection
April 2018
Cybersecurity best practices, artificial intelligence, robotic additive manufacturing, embedded systems, IIoT integration, energy efficiency
Edge Computing
This article collection contains several articles on how today's technologies heap benefits onto an edge-computing architecture such as faster computing, better networking, more memory, smarter analytics, cloud-based intelligence, and lower costs.
IIoT: Machines, Equipment, & Asset Management
Articles in this digital report highlight technologies that enable Industrial Internet of Things, IIoT-related products and strategies.
PLCs
Programmable logic controllers (PLCs) represent the logic (decision) part of the control loop of sense, decide, and actuate. Featured articles in this digital report compare PLCs and programmable automation controllers (PACs), industrial PCs, and robotic controllers.
SIDB

Find and connect with the most suitable service provider for your unique application. Start searching the Global System Integrator Database Now!

June 2018
Machine learning, produced water benefits, progressive cavity pumps
April 2018
ROVs, rigs, and the real time; wellsite valve manifolds; AI on a chip; analytics use for pipelines
February 2018
Focus on power systems, process safety, electrical and power systems, edge computing in the oil & gas industry
John O. Ayuk, PE, CFSE, PMP, CAP
Automation Engineer; Wood Group
Doug Baker
System Integrator; Cross Integrated Systems Group
Jose S. Vasquez, Jr.
Jose S. Vasquez, Jr.
Fire & Life Safety Engineer; Technip USA Inc.
Data Centers: Impacts of Climate and Cooling Technology
This course focuses on climate analysis, appropriateness of cooling system selection, and combining cooling systems.
Safety First: Arc Flash 101
This course will help identify and reveal electrical hazards and identify the solutions to implementing and maintaining a safe work environment.
Critical Power: Hospital Electrical Systems
This course explains how maintaining power and communication systems through emergency power-generation systems is critical.
Engineers' Choice Awards
The Engineers' Choice Awards highlight some of the best new control, instrumentation and automation products as chosen by Control Engineering subscribers.
System Integrator Giants
The System Integrator Giants program lists the top 100 system integrators among companies listed in CFE Media's Global System Integrator Database.
System Integrator of the Year
Each year, a panel of Control Engineering and Plant Engineering editors and industry expert judges select the System Integrator of the Year Award winners in three categories.
How to Maximize Factory Automation Efficiency with Low Cost Machine Vision
This eGuide illustrates solutions, applications and benefits of machine vision systems.
Wireless Reliability in Harsh Environments
Learn how to increase device reliability in harsh environments and decrease unplanned system downtime.
Human Factors and the Impact on Plant Safety
This eGuide contains a series of articles and videos that considers theoretical and practical; immediate needs and a look into the future.
June 2018
Discrete and process sensor fundamentals, autotuning controls, system integrator roundtable
May 2018
Salary and Career Survey, IT and OT convergence, robotic standards and safety, secure circuit protection
April 2018
Cybersecurity best practices, artificial intelligence, robotic additive manufacturing, embedded systems, IIoT integration, energy efficiency
Edge Computing
This article collection contains several articles on how today's technologies heap benefits onto an edge-computing architecture such as faster computing, better networking, more memory, smarter analytics, cloud-based intelligence, and lower costs.
IIoT: Machines, Equipment, & Asset Management
Articles in this digital report highlight technologies that enable Industrial Internet of Things, IIoT-related products and strategies.
PLCs
Programmable logic controllers (PLCs) represent the logic (decision) part of the control loop of sense, decide, and actuate. Featured articles in this digital report compare PLCs and programmable automation controllers (PACs), industrial PCs, and robotic controllers.
SIDB

Find and connect with the most suitable service provider for your unique application. Start searching the Global System Integrator Database Now!

June 2018
Machine learning, produced water benefits, progressive cavity pumps
April 2018
ROVs, rigs, and the real time; wellsite valve manifolds; AI on a chip; analytics use for pipelines
February 2018
Focus on power systems, process safety, electrical and power systems, edge computing in the oil & gas industry
John O. Ayuk, PE, CFSE, PMP, CAP
Automation Engineer; Wood Group
Doug Baker
System Integrator; Cross Integrated Systems Group
Jose S. Vasquez, Jr.
Jose S. Vasquez, Jr.
Fire & Life Safety Engineer; Technip USA Inc.
Data Centers: Impacts of Climate and Cooling Technology
This course focuses on climate analysis, appropriateness of cooling system selection, and combining cooling systems.
Safety First: Arc Flash 101
This course will help identify and reveal electrical hazards and identify the solutions to implementing and maintaining a safe work environment.
Critical Power: Hospital Electrical Systems
This course explains how maintaining power and communication systems through emergency power-generation systems is critical.
click me