This sample was developed by Control Engineering and sent to 14 control system supplier companies with batch product focus requesting participation in this article.
04g40301.gif (28256 bytes)


04g40301b.gif (54518 bytes)


The sample application was developed from material provided in Guidelines for Safe Automation of Chemical Processes published by Center for Chemical Process Safety of the American Institute of Chemical Engineers (New York, N.Y.). This sample was written and presented in a manner similar to what many service estimators receive from users. Using the drawings and written information, please prepare a

The unrelated detail often shown on Process Flow Diagrams (PFDs) and Piping and Instrumentation Diagrams (P&IDs) has not been included in this sample application. The purpose of this example is to develop time estimates to implement the process control shown. There is no assurance that this batch unit could produce PVC (polyvinyl chloride).

Simplified process description
The manufacturer of PVC from monomer is a relatively straightforward application. The reactor is the heart of the process. A batch requires about 10 hours. While the contents are agitated, the circulation of cooling water through the reactor jacket removes heat created by the exothermic reaction. To provide a continuous feed of PVC from the facility, four identical reactors are present. To minimize control software support and maintenance, the software should be developed so it can run on any of the four reactors without modification.

If the reactor has been opened for maintenance, it must be evacuated to remove any residual air (oxygen) to minimize oxidation reaction of monomer which may lead to stress corrosion damage to the reactor and/or poor product quality. Otherwise, the first step is to treat the reactor with antifoulant solution to prevent polymerization on the reactor walls. The antifoulant charge is followed with a demineralized water and surfactants charge. Liquid vinyl chloride monomer (VCM) is added at its vapor pressure (about 56 psig (3.86 bars) at 70°F (21°C)). The reaction initiator is liquid peroxide that is dissolved in a solvent. Because it is fairly active, it is stored at cold temperatures in a special bunker. Small quantities are removed for daily process use and are kept in a freezer. To ensure correct quantity additions of initiator, a small charge pot is manually filled.

Following the initiator, steam-heated water is applied to the reactor jacket to raise the temperature to about 130-140°F (54-60°C) (depending on the batch recipe for the particular grade of product). Agitation is necessary to suspend and control particle size of the VCM in the water, improve heat transfer throughout the batch, and produce a uniform product. Because the reaction is exothermic, once the reaction begins, the steam-heated water must be shutoff and cooling water circulated through the reactor jacket to control reactor temperature. The reaction is complete when reactor pressure decreases. Reacted polymer is dumped from the reactor and sent to downstream process units for residual VCM recovery, stripping, dewatering, and drying.

Pre-evacuation of air: If the reactors have been opened for maintenance, oxygen must be removed from the system for quality and metallurgical integrity reasons. This is done using steam ejectors to pull a vacuum.

Reactor preparation: The empty reactor is high-pressure water rinsed, leak tested, and treated with antifoulant.

Demineralized water charging: A controlled charge of water is added. An overcharge might lead to a hydraulic overfill; and undercharge may cause quality problems and potential reaction runaway. Any surfactants or other additives are introduced.

VCM charging: An accurate charge of VCM is added to the reactor.

Reactor heatup: The initiator is added from the charge pot, and cooling water is steam heated until it reaches 130-140°F (54-60°C) (10°F below steady-state reaction temperature).

Reaction: The steam system is isolated and cooling water is circulated to remove the heat created by the formation of the polymer. Water flow must be continuously adjusted to maintain the polymer at about 125°F (51°C).

Termination: When the reactor pressure starts to decrease, it is assumed most of the VCM has been consumed by the polymerization. The batch is ready to dump.

Reactor discharge: The reactor contents are dumped under pressure to a downstream holding facility where the product is degassed for subsequent stripping and drying. To prevent resin settling in the reactor, the agitator operates during the dumping process.

Two emergency processing steps are required.

Shortstop (chain stopper): Polymerization is stopped when the shortstop chemical is dumped into the reactor. The shortstop chemical is manually loaded into the shortstop vessel and pressurized with N 2 . When the shortstop chemical is dumped into the reactor, the agitator should continue to operate. If the agitator has failed, the shortstop chemical must be dumped into the reactor within one minute. If the shortstop chemical cannot be added, 'burping' the reactor- dropping the reactor pressure to form bubbles within the bulk liquid mass can stop polymerization.

Uncontrolled reaction: If cooling water flow is insufficient to remove the reaction heat and the liquid polymer temperature is 10°F (operator adjustable) above the temperature control setpoint, it is assumed a run-away reaction is occurring. Depressurizing the reactor will safely limit the reaction.

Process in S88 terminology
Control Modules
TagInputsOutputsService
XCV12 DIs1 Latching-DOSteam addition valve
XCV22 DIs1 Latching-DOHigh pressure water addition valve
XCV32 DIs1 Latching-DOShortstop chemical addition valve
XCV42 DIs1 Latching-DOReactor bottom valve
XCV52 DIs1 Latching-DOLiquid VCM addition valve
XCV62 DIs1 Latching-DORecycled VCM addition valve
XCV72 DIs1 Latching-DODepressurization valve
XCV82 DIs1 Latching-DOPre-evacuation valve
XCV92 DIs1 Latching-DOPost-evacuation valve
XCV102 DIs1 Latching-DOAdditive 1 addition valve
XCV112 DIs1 Latching-DOAdditive 2 addition valve
XCV122 DIs1 Latching-DOFlush water addition valve
XCV132 DIs1 Latching-DOInitiator addition valve
PI11 AIShortstop vessel pressure transmitter
PI21 AIReactor pressure transmitter
PI31 AICooling water pressure
PMP11 DI2 Momentary-DOCooling water pump
MTR11 DI2 Momentary-DOReactor agitator
FQI11 AICooling water flow transmitter. Totalization to occur in software.
LSL11 DIReactor low level switch
LSH11 DIReactor high level switch
TI11 AIReactor cooling water discharge temperature (RTD)
WQI11 AIReactor weight (load cells). Totalization to occur in software.
TIC11 AI (RTD)Reactor product temperature. Loop is primary in cascade control with FIC1.
FIC1FQI11 AOCooling water flow control. Loop is secondary in cascade control with TIC1.

 

Equipment Modules
NameControl ModulesOperational Description
HEADER1XCV7 XCV8
XCV9
Interface provided with four setpoints of: ALL CLOSED, DEGAS, PRE-EVACUATE, POST-EVACUATE. ALL CLOSED: All valves are commanded and verified OFF. If any valve fails to verify OFF, a unique alarm should be generated.
DEGAS: All valves are commanded and verified OFF. Only after all valves have verified OFF, XCV7 is commanded and verified ON. If XCV8 or XCV9 fails to verify OFF, or XCV7 fails to verify ON, a unique alarm should be generated and all valves commanded OFF.
PRE-EVACUATE: All valves are commanded and verified OFF. Only after all valves have verified OFF, XCV8 is commanded and verified ON. If XCV7 or XCV9 fails to verify OFF, or XCV8 fails to verify ON, a unique alarm should be generated and all valves commanded OFF.
POST-EVACUATE: All valves are commanded and verified OFF. Only after all valves have verified OFF, XCV9 is commanded and verified ON. If XCV7 or XCV8 fails to verify OFF, or XCV9 fails to verify ON, a unique alarm should be generated and all valves commanded OFF.
HEADER2XCV10 XCV11
XCV12
XCV13
Interface provided with four setpoints of: ALL CLOSED, ADD 1, ADD 2, WATER FLUSH, INITIATOR. ALL CLOSED: All valves are commanded and verified OFF. If any valve fails to verify OFF, a unique alarm should be generated.
ADD 1: All valves are commanded and verified OFF. Only after all valves have verified OFF, XCV10 is commanded and verified ON. If XCV11, XCV12, or XCV13 fails to verify OFF, or XCV10 fails to verify ON, a unique alarm should be generated and all valves commanded OFF.
ADD 2: All valves are commanded and verified OFF. Only after all valves have verified OFF, XCV11 is commanded and verified ON. If XCV10, XCV12, or XCV13 fails to verify OFF, or XCV11 fails to verify ON, a unique alarm should be generated and all valves commanded OFF.
WATER FLUSH: All valves are commanded and verified OFF. Only after all valves have verified OFF, XCV12 is commanded and verified ON. If XCV10, XCV11, or XCV13 fails to verify OFF, or XCV12 fails to verify ON, a unique alarm should be generated and all valves commanded OFF.
INITIATOR: All valves are commanded and verified OFF. Only after all valves have verified OFF, XCV13 is commanded and verified ON. If XCV10, XCV11, or XCV12 fails to verify OFF, or XCV13 fails to verify ON, a unique alarm should be generated and all valves commanded OFF.

Additional Information for Purposes of Estimating:
  1. Assume there are three additional batch reactor units (four total) as described above.

  2. Assume each reactor requires one main graphic and one support graphic.

  3. Assume there will be four product recipes, with three product grades per recipe, and each grade contains 15 variables that can be adjusted by the operator prior to starting a batch. Also, assume recipes operate only on the batch reactors. (e.g., Donuts = one product recipe. Apple jelly filled, grape jelly filled, and cream filled = three product grades.)

  4. Assume all other equipment shown on the PFD is outside the scope of this estimate.

  5. Assume each batch requires automatic generation of a batch-end report showing start and end times for the batch; start and end time for each phase, and start and end time each time an operator HOLDS and RELEASES a phase along with operator entered comments on why the HOLD was initiated.

  6. Assume each batch-end report includes an alarm history including when the alarm occurred and when it clears.

  7. Assume each batch report can be requested by the operator anytime during the batch (partial report) without compromising data for the final batch-end report. (No matter how many partial batch reports are requested, all data must be retained for inclusion in the final batch-end report.)


This concludes the information provided for purposes of estimating.

The following table indicates the information required by different control system vendors to prepare an estimate.

Requirements for Estimate Preparation
Vendor
A B CDEFGHIJK
Hardware/software platformXX
# & type of foreign device interfacesXXX
Total # of graphicsXXXXX
PFDsXXXXXX
P&IDsXXX
Site/Bldg. planX
Process descriptionXXXXXXX
RecipesXXXXXXX
Standard operating proceduresX
Reporting requirementsXXXX
Information management requirementsX
Total I/O countXXXXXXXXX
# & type of equipment and control modules per unitXXXXX
# & type of unitsXXXXXX
# of type process cellsXXXX
# & type of operationsXXXXXX
# of control modules per operationXXXX
# of unit proceduresXXXX
# of operations per unit procedureXXXXX
Testing requirementsX
ScheduleX
Project support requirementsXXXX
Additional requirements for
Hardware/software platformXXX
P&IDsXX
# & type of graphicsXX
Phase logic descriptions including abnormal situation handlingXXXXXXXX
Flow charts of recipesXXX
Foreign device interfacesX
Complexity of basic control (i.e., SAMA, Cause & effect diagrams, etc.)XXXXXX
Detail batch reporting requirementsXXXXX
Detailed functional specificationXXX
Required support activities (i.e., training, startup, etc.)XXXXX





The Engineers' Choice Awards highlight some of the best new control, instrumentation and automation products as chosen by Control Engineering subscribers. Vote now (if qualified)!
The System Integrator Giants program lists the top 100 system integrators among companies listed in CFE Media's Global System Integrator Database.
Each year, a panel of Control Engineering and Plant Engineering editors and industry expert judges select the System Integrator of the Year Award winners in three categories.
This eGuide illustrates solutions, applications and benefits of machine vision systems.
Learn how to increase device reliability in harsh environments and decrease unplanned system downtime.
This eGuide contains a series of articles and videos that considers theoretical and practical; immediate needs and a look into the future.
Maximize ROI with integrated control system approach; Microcontrollers vs. PLCs; Power quality; Accelerate and rewire IIoT; Traits for excellent engineers
HMI effectiveness; Distributed I/O; Engineers' Choice Award finalists; System Integrator advice; Inside Machines
Women in engineering; Engineering Leaders Under 40; PID benefits and drawbacks; Ladder logic; Cloud computing
Programmable logic controllers (PLCs) represent the logic (decision) part of the control loop of sense, decide, and actuate. As we know, PLCs aren’t the only option for making decisions in a control loop, but they are likely why you’re here.
This digital report explains how plant engineers and subject matter experts (SME) need support for time series data and its many challenges.
This article collection contains several articles on how advancements in vision system designs, computing power, algorithms, optics, and communications are making machine vision more cost effective than ever before.

Find and connect with the most suitable service provider for your unique application. Start searching the Global System Integrator Database Now!

Control room technology innovation; Practical approaches to corrosion protection; Pipeline regulator revises quality programs
Cloud, mobility, and remote operations; SCADA and contextual mobility; Custom UPS empowering a secure pipeline
Infrastructure for natural gas expansion; Artificial lift methods; Disruptive technology and fugitive gas emissions
Automation Engineer; Wood Group
System Integrator; Cross Integrated Systems Group
Jose S. Vasquez, Jr.
Fire & Life Safety Engineer; Technip USA Inc.
This course focuses on climate analysis, appropriateness of cooling system selection, and combining cooling systems.
This course will help identify and reveal electrical hazards and identify the solutions to implementing and maintaining a safe work environment.
This course explains how maintaining power and communication systems through emergency power-generation systems is critical.
The Engineers' Choice Awards highlight some of the best new control, instrumentation and automation products as chosen by Control Engineering subscribers. Vote now (if qualified)!
The System Integrator Giants program lists the top 100 system integrators among companies listed in CFE Media's Global System Integrator Database.
Each year, a panel of Control Engineering and Plant Engineering editors and industry expert judges select the System Integrator of the Year Award winners in three categories.
This eGuide illustrates solutions, applications and benefits of machine vision systems.
Learn how to increase device reliability in harsh environments and decrease unplanned system downtime.
This eGuide contains a series of articles and videos that considers theoretical and practical; immediate needs and a look into the future.
Maximize ROI with integrated control system approach; Microcontrollers vs. PLCs; Power quality; Accelerate and rewire IIoT; Traits for excellent engineers
HMI effectiveness; Distributed I/O; Engineers' Choice Award finalists; System Integrator advice; Inside Machines
Women in engineering; Engineering Leaders Under 40; PID benefits and drawbacks; Ladder logic; Cloud computing
Programmable logic controllers (PLCs) represent the logic (decision) part of the control loop of sense, decide, and actuate. As we know, PLCs aren’t the only option for making decisions in a control loop, but they are likely why you’re here.
This digital report explains how plant engineers and subject matter experts (SME) need support for time series data and its many challenges.
This article collection contains several articles on how advancements in vision system designs, computing power, algorithms, optics, and communications are making machine vision more cost effective than ever before.

Find and connect with the most suitable service provider for your unique application. Start searching the Global System Integrator Database Now!

Control room technology innovation; Practical approaches to corrosion protection; Pipeline regulator revises quality programs
Cloud, mobility, and remote operations; SCADA and contextual mobility; Custom UPS empowering a secure pipeline
Infrastructure for natural gas expansion; Artificial lift methods; Disruptive technology and fugitive gas emissions
Automation Engineer; Wood Group
System Integrator; Cross Integrated Systems Group
Jose S. Vasquez, Jr.
Fire & Life Safety Engineer; Technip USA Inc.
This course focuses on climate analysis, appropriateness of cooling system selection, and combining cooling systems.
This course will help identify and reveal electrical hazards and identify the solutions to implementing and maintaining a safe work environment.
This course explains how maintaining power and communication systems through emergency power-generation systems is critical.
The Engineers' Choice Awards highlight some of the best new control, instrumentation and automation products as chosen by Control Engineering subscribers. Vote now (if qualified)!
The System Integrator Giants program lists the top 100 system integrators among companies listed in CFE Media's Global System Integrator Database.
Each year, a panel of Control Engineering and Plant Engineering editors and industry expert judges select the System Integrator of the Year Award winners in three categories.
This eGuide illustrates solutions, applications and benefits of machine vision systems.
Learn how to increase device reliability in harsh environments and decrease unplanned system downtime.
This eGuide contains a series of articles and videos that considers theoretical and practical; immediate needs and a look into the future.
Maximize ROI with integrated control system approach; Microcontrollers vs. PLCs; Power quality; Accelerate and rewire IIoT; Traits for excellent engineers
HMI effectiveness; Distributed I/O; Engineers' Choice Award finalists; System Integrator advice; Inside Machines
Women in engineering; Engineering Leaders Under 40; PID benefits and drawbacks; Ladder logic; Cloud computing
Programmable logic controllers (PLCs) represent the logic (decision) part of the control loop of sense, decide, and actuate. As we know, PLCs aren’t the only option for making decisions in a control loop, but they are likely why you’re here.
This digital report explains how plant engineers and subject matter experts (SME) need support for time series data and its many challenges.
This article collection contains several articles on how advancements in vision system designs, computing power, algorithms, optics, and communications are making machine vision more cost effective than ever before.

Find and connect with the most suitable service provider for your unique application. Start searching the Global System Integrator Database Now!

Control room technology innovation; Practical approaches to corrosion protection; Pipeline regulator revises quality programs
Cloud, mobility, and remote operations; SCADA and contextual mobility; Custom UPS empowering a secure pipeline
Infrastructure for natural gas expansion; Artificial lift methods; Disruptive technology and fugitive gas emissions
Automation Engineer; Wood Group
System Integrator; Cross Integrated Systems Group
Jose S. Vasquez, Jr.
Fire & Life Safety Engineer; Technip USA Inc.
This course focuses on climate analysis, appropriateness of cooling system selection, and combining cooling systems.
This course will help identify and reveal electrical hazards and identify the solutions to implementing and maintaining a safe work environment.
This course explains how maintaining power and communication systems through emergency power-generation systems is critical.
click me