Some fruits of our labor are finally beginning to appear. The engineering staff did well to get the SCADA servers installed and running at the data center this past week. As I write this, the first of the upgraded existing RTUs is being installed at a pump station. The SCADA interface is taking form, though definitely still in the beta phase. We expect to have news next week regarding a public access period to the site.